Rock Springs Road Bridge Over Mojave River Passes Halfway Mark

AI Assisted Icon
Published on September 05, 2026
Rock Springs Road Bridge Over Mojave River Passes Halfway MarkRock Springs Rd. — Bridge Construction Halfway Complete
Google Street View

The long-awaited Rock Springs Road Bridge over the Mojave River is now more than halfway built, with construction crews working toward a final concrete pour on the $19.2 million span connecting Apple Valley and Hesperia. The project replaces a two-lane low-water crossing built in 1963.

According to the Victorville Daily Press, the bridge project sits on Rock Springs Road between Glendale Avenue and Deep Creek Road, crossing the Mojave River at a point long notorious for washouts. The supplied Pain In The Pass page does not contain reporting about the old Rock Springs Road crossing; its scraped content concerns a motorcyclist injured in a Cajon Pass crash.

The stretch of roadway being upgraded is no minor side street. It is the crossing between Apple Valley and Hesperia. The crossing has faced at least one temporary closure during a rescue.

Modern Safety Features Built Into the New Span

The replacement bridge is being engineered to modern safety and seismic standards, according to the same reporting. The design calls for two full-width lanes with four-foot shoulders and a concrete-barricaded sidewalk with streetlighting — a substantial upgrade from the narrow pavement it replaces.

The construction contract went to M.C.M. Construction, Inc., with a bid opening held July 17, 2025. The project draws on federal funding through the Federal Highway Administration and Caltrans grant programs, which comes with strings attached: subcontracts must meet a 22% Disadvantaged Business Enterprise participation target, according to contract documentation reviewed by HigherGov.

Environmental Reviews Along the River Corridor

Because the bridge alignment runs through the Mojave River's riparian corridor, environmental oversight required pre-construction surveys for protected desert tortoises and nesting birds. An Incidental Take Permit was issued in June 2026 under California's Western Joshua Tree Conservation Act, according to filings logged with CEQAnet, formalizing the project's compliance with state species-protection statutes before heavy construction could proceed in earnest.

The stakes behind those environmental and engineering requirements are not abstract. High-intensity storms have repeatedly triggered swiftwater emergency responses at the low-water crossing, including a May 2023 incident in which San Bernardino County firefighters extracted a driver trapped in moving Mojave River waters, according to the Victor Valley News Group. Hydrological modeling from the National Water Prediction Service has found that high-flow discharges on the Mojave River near Victorville repeatedly cause levee erosion and road overtopping along Rock Springs Road during winter storms, underscoring why the old pavement structure kept failing.

Timeline to Completion

The Rock Springs Road span remains under construction.

For now, the milestone is a construction one: crews are working toward the final concrete pour needed to complete the new structure, according to the Daily Press. Once finished, the bridge is expected to give Apple Valley and Hesperia residents a permanent, all-weather link across the Mojave River, replacing the existing crossing.