Shelby Drive Set to Reopen in Collierville With Ribbon-Cutting Monday, Nov. 2

AI Assisted Icon
Published on October 30, 2026
Shelby Drive Set to Reopen in Collierville With Ribbon-Cutting Monday, Nov. 2Source: Chase Via / Wikimedia Commons

Collierville has scheduled a ribbon-cutting for Monday, November 2, 2026, to mark the reopening of Shelby Drive, a stretch of roadway that has been under construction as part of a major widening project between Sycamore Road and Highway 72. The road is set to officially reopen to traffic after that ceremony.

The Shelby Drive Improvements Project has transformed the former two-lane road into a four-lane, median-divided street, according to Action News 5. The Town of Collierville has said the road work is complete seven months ahead of schedule, per the station's report. The project’s completion timeline has shifted over time.

What the Widened Road Includes

Beyond adding travel lanes, the project includes a replacement bridge just east of Fire Station 6 and a major drainage culvert at Quinn Road, the station reports. Crews also upgraded water, sewer and irrigation utilities along the corridor as part of the work.

The finished roadway is also set to bring new street lighting, bike lanes, curbs, gutters and sidewalks, along with a modernized traffic signal at the intersection of Shelby Drive and Highway 72, per the same account. Memphis Light, Gas and Water will install street lighting in the medians at a later time, according to the report.

From Heavy Equipment to Finishing Touches

Just weeks before the ribbon-cutting, the project had already shifted into a cleanup phase. According to an earlier Action News 5 report, most large equipment, including cranes and bulldozers, had left the site after the heavy construction phase wrapped up. Crews were instead focused on fine-tuning the irrigation system, completing sod in the medians, finish-grading and other site cleanup tasks.

That same report said final paving and striping were scheduled for the weeks of October 12 and October 19, weather permitting, and that the road was expected to open to traffic during the last week of October or the first week of November. The newly announced Monday ribbon-cutting falls right within that window.

A Years-Long Project With a Shifting Timeline

The scale of the undertaking has been significant from the start. As reported by WREG, the project widened the roadway from just east of Sycamore Road to Highway 72 into a four-lane, median-divided urban street, with work including the replacement of two bridges, installation of major drainage culverts, upgraded utilities, new street lighting and bike lanes, curbs, gutters and sidewalks, along with the traffic signal modernization. The outlet described the effort as part of a joint infrastructure initiative with the Memphis Metropolitan Planning Organization and the Tennessee Department of Transportation.

Project timelines have shifted over time. WREG had reported the entire project would be completed by December 2026, calling that roughly five months ahead of schedule, while a Town of Collierville update separately indicated the entire four-lane, median-divided roadway, complete with sidewalks and updated traffic signals, was scheduled to be fully finished and open by the end of December 2026, weather permitting. A town update also pointed to continuing heavy rainfall as a factor affecting the schedule, citing construction of a concrete box culvert for the bridge near Quinn Road as one example. The Town of Collierville's more recent statement that work is complete seven months ahead of schedule reflects an updated assessment tied to this week's planned ribbon-cutting rather than those earlier projections.

The Collierville Board of Mayor and Aldermen voted on March 24 to award a $14,208,766.11 construction contract for the widening project, according to CitizenPortal.ai, with the town's share of that cost coming to about $4.9 million. Earlier coverage from the Daily Memphian in May 2025 had described the East Shelby Drive expansion as a project expected to last two years and include the replacement of two bridges, underscoring just how long area drivers have waited for this stretch of road to reopen.