American Canyon's city council is scheduled to vote today on a $704,395 contract bid for a new pathway along Green Island Road, a project that would plug the city into the sprawling Napa Valley Vine Trail network. The roughly 0.8-mile stretch between Devlin and Paoli Loop roads would become a Class I multiuse trail, giving cyclists and pedestrians a dedicated route through one of the city's busiest industrial corridors.
The vote, reported by The Napa Valley Register, would award the contract to Martin Brothers Construction, which submitted the lowest bid among 13 competing firms. City staff recommended the bid because it fell within the projected $1,193,000 budget for the pathway contract and met all work criteria, according to the same report. American Canyon solicited bids for the work on Sept. 18.
If approved, American Canyon would be poised to build a critical section of the Napa Valley Vine Trail, a planned 47-mile path connecting the Vallejo Ferry Terminal to Calistoga, linking the city to recreational spaces across the valley, per the Register's reporting. The new trail section is designed to include flashing crosswalk lights and striping, features meant to keep foot and bike traffic visible along a road that cuts through American Canyon's economic hub of warehouses and industrial facilities.
Why a Busy Industrial Road Needs Safer Crossings
Carlotta Sainato, program manager of the Napa County Bicycle Coalition, praised the trail design's focus on pedestrian and cyclist safety and accessibility, the Register reported. “It's the kind of structure you want on a busy industrial road,” Sainato said, according to the outlet. Green Island Road has not seen a significant upgrade since the late 1980s, making the safety additions especially notable for a corridor that sees steady truck and warehouse traffic.
Shawn Casey-White called Green Island Road an important connection of the Vine Trail, saying the connection will be fantastic, per the Register's account. Construction on the pathway segment is expected to start in late December, the outlet reported, once the contract is finalized.
Project Delays and a Rising Budget
The broader Green Island Road redevelopment project, which will widen nearly two miles of roadway and includes new sidewalks and additional traffic safety features, has had a far bumpier path to this point. The project was initially projected to cost around $14 million back in 2019, but American Canyon increased the project's budget by roughly 61%, to $22.6 million this past August, according to the Register's reporting. City officials attributed the jump to unexpected infrastructure-condition, traffic-mitigation and staffing costs.
Part of the delay traces to Caltrans, which held off on sign-off for continuation of work in order to address underground utility conflicts affecting the original design, per the same report. American Canyon completed major utility and road work for the Green Island Road project last summer, clearing one of the hurdles that had stalled progress. The project draws most of its funding from federal grants, voter-approved local transportation measures, Green Island property-owner bond financing and city utility funds, the Register noted.
A Small Link in a Much Longer Trail
The Green Island Road pathway would fill in a small but strategic piece of a much larger regional effort. The Vine Trail Coalition and local governments are working to complete the final 14 miles of the 47-mile vision in two key sections — Yountville to St. Helena and American Canyon to the City of Napa — according to vinetrail.org. The 11-mile Yountville-to-St. Helena stretch is currently in the engineering stage, while a planned 3-mile Vista Carneros connection would join the existing Riversound Vine Trail segment through Napa's Kennedy Park to American Canyon on Devlin Road.
Momentum on the broader trail has been building. In 2025 alone, two new sections opened — one connecting Vallejo to American Canyon and another linking St. Helena to Calistoga at 8.2 miles — per vinetrail.org. Chuck McMinn, speaking to the Press Democrat, said more than half a million people use the Vine Trail every year, and that 70% of those users live in Napa or Solano counties. That outlet reported a 7.5-mile stretch connecting American Canyon with the Vallejo Ferry Terminal opened in March 2025, while a separate snippet from the Napa Valley Transportation Authority describes a 5.5-mile segment linking the two communities as expected to finish this fall — the available records don't clarify how the two figures relate. The Press Democrat has reported the full 47-mile trail, from Vallejo to Calistoga, is expected to be complete by 2028.
For now, American Canyon's piece of that vision comes down to today's vote. Whether the council approves the Martin Brothers Construction bid will determine if shovels hit Green Island Road as soon as late December.