Greater Des Moines/ Parks & Nature

Ankeny Covers High Trestle Flowline Ahead of December Opening

AI Assisted Icon
Published on November 17, 2026
Ankeny Covers High Trestle Flowline Ahead of December OpeningSource: blmcalifornia / Wikimedia Commons

Ankeny's newest stretch of the High Trestle Trail Experience Park is poured, covered, and still off limits. Contractors have laid undulating concrete for a roller-coaster-like flowline beside the conventional flat bike trail, then blanketed it with dirt so riders cannot try the hills before the surface cures. The path is going in along the High Trestle Trail as an alternative to the straight, level ride already there.

December is the opening now expected, one piece of a wider set of projects aimed at bike tourism and safer crossings. KCCI reported that the flowline is unique in Central Iowa's trail system. Economic Development Director Derek Lord said it should attract attention and bring visitors to Ankeny.

Hills Beside the Flat Trail

The route is short on purpose. In January, Axios described a nearly 900-foot paved path built off the High Trestle Trail, with small rising and falling hills, planned just east of Walnut Street. The plan called it accessible to families pushing strollers, wheelchair users, and children on bikes.

The roller-coaster comparison is about the profile, not the audience. Small hills, a paved surface, and the ordinary flat trail still sitting alongside. Riders who want the familiar High Trestle alignment do not have to take the new path. It is an optional side route, not a reroute of the main trail.

That January account expected the flowline by the end of summer. KCCI's account this week has the concrete curing under a dirt cover and the opening set for December. The cover has one job: keeping people off the path while it cures. The shape is already in the ground. The surface is not ready to ride.

Lord has tied the novelty to visitation, a feature he expects will get noticed because the city describes it as unlike anything else in Central Iowa's trail system. Nearly 900 feet is also a different scale from what the park has already built. It runs roughly twice the length of a glow-in-the-dark walking offshoot added in an earlier phase.

What the First Phase Built

The flowline is a later piece of a 14-acre park the city plans to expand over time, with the stated goal of making Uptown an outdoor tourism destination. The first construction phase was the larger contract. In August 2024, the City Council approved a $1 million deal with Mainline Construction of Bondurant, the low bidder, to begin the High Trestle Trail transformation, the Des Moines Register reported.

By May 2025, that phase had a visible result. Visitors could walk a 425-foot offshoot of the High Trestle Trail paved with glow-in-the-dark material, the Register reported. The $1 million first phase also included native plantings, trees, and new lighting. The glow path is a walking offshoot. The flowline now curing beside the trail is the riding alternative.

The phase Axios described in January sat at another scale, around $300,000. Ankeny had a $100,000 grant from Polk County and $45,000 from the Bravo arts council, $145,000 of that phase estimate. Plans attached to the phase included pocket play areas, benches, and an interactive LED installation in the underpass beneath South Ankeny Boulevard. The $300,000 figure is the reported cost of a park phase, not a standalone price for the flowline.

Lights Under the Boulevard

The underpass has a schedule of its own. Ankeny is installing new lighting in the bike-trail tunnel under South Ankeny Boulevard, KCCI reported. Some of those lights will be motion-controlled and will change color depending on bike traffic. The lighting project is slated for completion in spring 2027.

Lord said the tunnel lighting is an unexpected feature and will distinguish the experience park. January's plans had already put an interactive LED installation in that same underpass. The newer account is more specific about the behavior. At least some lights respond to bikes moving through, and the color shifts with the traffic.

That tunnel is the passage the bike trail already uses to get under South Ankeny Boulevard. It is not the same project as the pedestrian tunnels planned at Oralabor Road. Those belong to the intersection work, and the city has compared them with tunnels at State Street and Oralabor nearby.

The timing splits the next pieces across two seasons. The flowline is expected in December. The tunnel lights are not slated to be finished until the following spring. A rider who gets the hills on the December schedule would still pass under the boulevard before the motion-controlled lighting is due.

Turn Lanes, Tunnels, and 2030

The traffic fix is the long one. Ankeny plans extra turn lanes and pedestrian tunnels at South Ankeny Boulevard and Oralabor Road, with the intersection upgrades scheduled to be finished in 2030. The pedestrian tunnels are expected to resemble the ones at State Street and Oralabor Road, a crossing pattern the city already uses nearby.

Public Works Director Mark Mueller said the extra turn lanes and pedestrian tunnels will help vehicles move through the intersection more quickly by avoiding pedestrian and bicycle signal phases. The crossings move into their own tunnels. Taking people on foot and on bikes out of those signal phases is how he says cars get through faster.

For riders, the planned tunnels are the other half of a program the city has framed as tourism and safety together. The flowline is the attraction. The Oralabor tunnels are supposed to be the separation, so a bike crossing does not have to share a signal phase with the cars Mueller is trying to keep moving. That piece carries a finish year at the end of the decade, not a date next to this winter's hills.

The Corridor Count and the Gaps

Council has already approved a broader remake of the street this park has to live with. Business Record reported that the Ankeny City Council signed off on a plan to revitalize the South Ankeny Boulevard corridor from First Street to Oralabor Road. Lord said more than 1,000 people took part in the public-input process. He has also said gaps in the trail network and sidewalk system still need to be addressed.

Oralabor Road is the south end of that approved corridor, and it is the intersection scheduled for the extra turn lanes and pedestrian tunnels. The lighting going in now is under South Ankeny Boulevard, in the trail tunnel the park already uses. The corridor plan and the experience park are stacked on the same boulevard, on different clocks.

The corridor plan also put a count on the audience. It reported that 551,800 people visited the corridor in 2024, for a total of 2.6 million visits. Those figures cover the boulevard corridor, not the High Trestle Trail alone. Alongside them, the city has described adding onto the 14-acre park over time so Uptown becomes an outdoor tourism destination.

Before any of that later work, the new concrete is the thing in the ground. It is formed into small hills just east of Walnut Street, hidden under dirt so it can cure, and expected in December beside the flat trail that is still the straightforward ride.