A $24.4 million harbor overhaul in Bayou La Batre has crossed the halfway point, with a 100-slip marina, new boat ramps and dockside pavilions slowly emerging along the waterfront. The City Docks redevelopment, funded through RESTORE Act dollars tied to the Deepwater Horizon recovery, broke ground in September 2025 and is contracted to wrap up by August 2027.
As reported by AL.com, the project includes new boat ramps, paved parking, a marina, pavilions and other amenities, and it's now past the halfway mark toward completion. Bayou La Batre Mayor Henry Barnes told the outlet he expects the harbor could open earlier than its contracted August 2027 date, though he said the city is still weighing whether to manage the finished harbor itself or bring in an outside management group. Barnes also said the harbor is designed to benefit the city without displacing the shrimp boat or shipyard industries that have long defined the bayou's working waterfront.
Matthew Jones, representing the project, said per contract the harbor is on schedule for an August 2027 finish, according to the same report. Ben M. Radcliff Contractor, Inc. is leading construction, with Moffatt & Nichol serving as the project's construction engineering and inspection firm.
What's Actually Getting Built
The finished harbor is meant to include a four-lane concrete boat ramp with courtesy docks, gangways, protective rock revetment and expanded paved parking, according to FOX10. Plans also call for a marine fueling station and a 4,200-square-foot multi-use building alongside the fixed dock for seafood sales, per Moffatt & Nichol's project description. A full-service marina with 100 slips is intended to serve recreational, charter and commercial vessels, according to Marina Dock Age.
Parking is a major piece of the plan, with room for 100 trucks and trailers and 240 passenger vehicle spaces for community events, per AL.com's report and the city's project page. Pavilions covering roughly 9,000 square feet are intended to host markets, seafood sales and community gatherings, the AL.com article notes. The Mobile County Commission awarded the $24.4 million construction contract for the project.
The Shoreline That's Protecting the New Harbor
Just next door sits Lightning Point, a separate coastal restoration effort that has helped protect the Bayou La Batre harbor from erosion that once put it at risk of being lost to coastal storms, according to AL.com's reporting. The Nature Conservancy began strategically buying up land there in 2015, with the restoration eventually including $6 million in land purchases and $16 million spent building marshland, per the same account. Most of that funding came from the National Fish and Wildlife Foundation's Gulf Environmental Benefit Fund, and the effort drew in The Nature Conservancy, the foundation, the City of Bayou La Batre, Alabama Power, Mobile County, the Mobile Bay National Estuary Program and the Alabama Department of Conservation and Natural Resources.
Construction on Lightning Point began in fall 2019, and by 2020 crews had completed seven of 11 breakwaters, two jetties and more than 40 acres of habitat restoration ahead of that year's hurricane season, according to The Nature Conservancy. The restoration's design incorporated 1.5 miles of offshore breakwaters, 40 acres of restored marsh and 10,000 linear feet of tidal creeks, per Moffatt & Nichol. A second phase was celebrated with a ribbon-cutting in 2022, ultimately creating 40 acres of marshland protected by segmented breakwaters.
Seven Years of Holding the Line
Construction on the restoration began in fall 2019. It survived four named storms in 2020 alone; Hurricane Nate, which made landfall near the mouth of the Mississippi River in October 2017, caused shoreline damage before restoration construction began. Officials involved say the project has helped demonstrate that coastal erosion can be reversed rather than simply managed.
The site now supports sheltered pools, tidal creeks, marine life and birds, according to the same reporting. The Nature Conservancy has used those sheltered pools to test oyster-related projects. The Lightning Point Shoreline Restoration was not fully completed until 2024, when the remaining four breakwaters were constructed. The Nature Conservancy, Moffatt & Nichol and the Dauphin Island Sea Lab have monitored the site.
For Bayou La Batre, the pairing of a restored shoreline and a rebuilt harbor is meant to safeguard both the working waterfront and the public spaces now rising beside it.