Brady Township supervisors voted Tuesday night to approve a new ordinance that sharply limits where data centers can be built and demands developers prove they have enough water before anything gets built. The rules, which run more than 20 pages, confine the facilities to a narrow strip of light industrial land along Route 8 and give the township board the power to reject any project that can't show an adequate water supply.
The board officially approved the measure at its monthly meeting on Tuesday, according to the Butler Eagle. Under the new rules, any proposed data center would only be allowed as a conditional use in the light industrial zoning district, a designation that covers just a small chunk of land along the highway corridor. The ordinance also spells out requirements for lot size, buffer yards and setbacks meant to keep the facilities at arm's length from neighboring properties.
Perhaps the most consequential provision is the one tied directly to water. The township will not approve a data center project at all if there isn't an adequate supply of water for its proposed use, per the same report. Developers would, however, be exempt from any requirement to use groundwater for cooling purposes if a public water source is available instead.
Nearly 20 Plans Required Before Shovels Hit Dirt
Township solicitor Tom Smith laid out just how much paperwork developers will face before construction could begin. “We're going to require them to provide us with, like, 20 different plans,” Smith said, according to the Butler Eagle's account of the meeting. Those plans cover traffic, landscaping, water consumption, post-construction well testing, wastewater disposal, emergency response and decommissioning.
The ordinance's broader studies requirement echoes that list, calling for documentation on electricity and water sourcing, potential environmental impact, noise and vibration, emergency response, and how a facility would eventually be decommissioned. Taken together, the paperwork load reflects a pattern seen elsewhere in Pennsylvania, where municipalities have leaned on conditional-use processes specifically so they can attach detailed, project-by-project conditions rather than approving data centers outright. The Penn State Center for Energy Law and Policy notes that many municipalities have chosen to restrict data center development to certain parts of town, most often industrial or commercial zones, which mirrors the approach Brady Township just adopted.
Other Butler-Area Townships Are Drawing Similar Lines
Brady Township isn't alone in moving on this front this month. A day earlier, Lancaster Township supervisors approved their own zoning amendment, permitting data centers only as a conditional use in the industrial zoning district there too. That ordinance requires a minimum 10-acre lot, 300-foot setbacks, an 80-foot buffer yard and a 55-decibel noise limit at property lines, according to the Butler Eagle's separate report on that vote.
Butler Township has taken a slightly different route, permitting data centers and accessory uses by special exception rather than conditional use, and only within its Industrial zoning district, as reported by the Times Leader. Further east, in central Pennsylvania, Gregg Township supervisors voted 3-0 in late October to approve a conditional-use application for a specific proposed data center, attaching 31 conditions that include a ban on using private groundwater wells or direct surface-water withdrawals for cooling, PennLive reported.
Why Water and Power Keep Coming Up
The emphasis on water isn't happening in a vacuum. An industry inventory from October counted 79 operating data centers across Pennsylvania, with seven more under construction and 46 planned, according to ENR. That same report cited an August poll showing six in ten likely Pennsylvania voters opposed building data centers to house artificial intelligence in the United States.
Statewide, the facilities' growing appetite for electricity and water has become a flashpoint as the state positions itself as an attractive location for AI infrastructure, according to WESA. A data center ordinance guide prepared by the Chester County and Montgomery County Planning Commissions recommends that municipalities require certified documentation from public water authorities confirming they can actually supply the water a proposed facility would need, and that energy usage plans cover annual electricity demand, supply sources, storage capacity and backup power. Brady Township's new ordinance, with its water-supply veto power and nearly two dozen required plans, lands squarely within that cautious, conditional-use trend taking hold across the region.