Cascade Township Pushes Burton Street Overpass to Late 2027, Still Awaits Federal Sign-Off

AI Assisted Icon
Published on November 13, 2026
Cascade Township Pushes Burton Street Overpass to Late 2027, Still Awaits Federal Sign-OffPatterson Ave. SE & Burton St. SE — Approximate End Of Planned Bridge
Google Street View

Cascade Township now expects construction on its long-planned pedestrian bridge over I-96 at Burton Street to begin in late 2027, a timeline that has slipped well past earlier projections as the project continues working through state and federal permitting. The overpass would give cyclists and pedestrians a dedicated crossing separate from vehicle traffic on a stretch of roadway that was never built with foot or bike traffic in mind.

According to the township's own project page, the bridge has already received permit approval from the Michigan Department of Environment, Great Lakes, and Energy, but it remains pending review by the Michigan Department of Transportation and the Federal Highway Administration, a process Cascade Township says typically takes four to six months. Once those reviews clear, the project is anticipated to go out to bid in mid to later winter, the township says. Officials also note the project carries a $3.5 million state funding appropriation that has been extended to accommodate the updated schedule.

The timeline marks a shift from earlier expectations. As MLive reported in September 2024, a township engineer at the time expected bidding to begin in spring 2025 with construction starting that fall, around the same meeting where the Cascade Township Board of Commissioners approved a $300,000 contract with engineering consultant Spaulding DeDecker to design the overpass. The outlet reported the bridge would be built as a separate structure on the south side of the existing Burton Street bridge, connecting pathways near Patterson Avenue and Highridge Lane, and that the engineer did not expect construction to cause long-term road closures.

Soil Testing Pushed the Schedule

Part of the delay traces to permitting requirements that forced a shift in the bridge's alignment. Per Citizen Portal, the Cascade Charter Township Board approved a $36,000 change order on Dec. 11 to pay for additional geotechnical soil borings, with officials describing the extra testing as necessary to complete MDOT permitting and keep the project on track for bidding the following winter.

FOX 17 reports that the project, authored by Cassandra Alonso, would extend the pathway on the Cascade Township side of I-96 and connect it to an existing pathway in Kentwood. The existing Burton Street bridge, which currently carries vehicles across I-96, has a narrow design that can make sharing the roadway challenging for pedestrians and cyclists, according to the outlet. Cascade Township Supervisor Grace Lesperance said the project reflects the township's goal of expanding pathway connections and improving access to surrounding communities, per FOX 17's reporting.

Construction Impacts Still Being Mapped Out

Township officials anticipate lane shifts along I-96 during construction and the possibility of one night closure of the interstate to install the prefabricated bridge, FOX 17 reports. Construction is expected to have minimal impacts along Burton Street itself and is anticipated to take four to five months once it begins, though officials caution the project timeline could still change as work progresses. No official construction start date has been established.

Kevin Cusack, who serves on the board of West Michigan Trails and says he uses the region's trail network nearly every day, told FOX 17 he supports getting bicycles out of narrow, shared spaces like the current Burton Street bridge. He said many West Michigan trails simply don't connect to one another, and that building links like the Burton Street overpass could let cyclists and pedestrians travel farther without gaps forcing them onto busy roads.

Part of a Broader Regional Push

The Burton Street project fits into a larger regional effort to stitch together non-motorized pathways across West Michigan. According to WalkBike.Info, an 18-county Regional Trails Master Plan aimed at connecting communities and destinations with multi-use pathways was completed in October 2024, following a process that kicked off with the West Michigan Trail Summit in October 2023 and included public input gathered over the summer before the plan was finalized that fall.