Colorado Springs Mayor Yemi Mobolade has rejected a proposed data center on city-owned land near the airport, a decision that became public this week. The project, known as Project Honey Badger, would have landed at Peak Innovation Park, and the developer behind it is now disputing the mayor's reasoning in sharp terms.
The rejection came to light after a public records request, according to KOAA News 5, which obtained a letter Mobolade sent to Urban Frontier, the master developer of Peak Innovation Park. In it, the mayor told Urban Frontier that the city did not wish to pursue the site as a data center, pointing to what he called the substantial energy demands associated with the proposed use.
Mobolade wrote that he does not believe the data center proposal is the right fit for Peak Innovation Park, and said he has a responsibility to steward the public asset and protect the long-term interests of the airport, residents, and the city's economy. He also said that, given growing local and national concerns surrounding data centers, he made the decision not to move forward with Project Honey Badger. Mobolade described the move as responsible economic development, not a retreat from economic development, and said the city remains committed to pursuing businesses that create jobs, strengthen the economy, use infrastructure responsibly, and contribute to long-term prosperity.
Developer Pushes Back Hard
Urban Frontier did not take the rejection quietly. In a letter sent back to the mayor and obtained by the station from an anonymous source, the developer wrote that it could not accept the rejection of the Honey Badger project as a reasonable exercise of the city's discretion under their agreement. The company questioned how Mobolade reached his conclusion and argued the data center would not have hurt the city's energy consumption.
According to the developer's letter, Project Honey Badger had already entered into discussions with Colorado Springs Utilities over power and a potential power purchase agreement that, in the company's telling, would have had no negative impact on the utility or the greater Colorado Springs community. Urban Frontier also said the project was meant to support the military at Peterson Space Force Base, and told the station it had spent more than a year working to include the data center in the business park. Urban Frontier, for its part, said Mobolade's stated reasoning for denying the opportunity was based on falsehoods.
News5 said it sent several questions to the mayor about the proposal but learned he was traveling to a conference at the time.
What's Already Built at Peak Innovation Park
Peak Innovation Park is a 1,600-acre business park near the Colorado Springs Airport, and Mobolade's statement noted it already has more than 5,000 people working there across roughly 4.7 million square feet of development. The mayor's statement pointed to existing and planned investments at the park, including Swire Coca-Cola's $475 million project, Forge at Peak Innovation Park, and a planned $50 million pecan-processing facility, as evidence the city is still committed to attracting businesses to the site.
A Citywide Debate Over Data Center Rules
The rejection lands amid a broader local reckoning over how Colorado Springs should regulate data centers. A report from the Romer Institute of Evidence-based Policy found the city already has some protections in place, including utility control, safeguards for large power users, noise limits, and water-use data covering seven data centers currently served by Colorado Springs Utilities, KOAA News 5 reported. The city is reviewing the report's recommendations, which came at no cost to Colorado Springs, per the same account.
That report identified 14 potential policy changes, including stronger rules around water use, noise, and where data centers can be built. Rather than calling for a moratorium, the report recommended tightening Colorado Springs' existing rules rather than halting new projects, according to Axios. Specific proposals included creating a separate land-use category for data centers, revisiting the 10-megawatt threshold that triggers utility safeguards, requiring independent noise studies, weighing limits on low-frequency sound, and formalizing water-use assessments, the outlet reported.
Colorado Springs isn't the only city wrestling with this. Denver and three Colorado counties have paused new data centers while they consider new regulations, KOAA News 5 reported. Elsewhere in the state, Longmont has banned hyperscale data centers outright, while Denver, Brighton, Lafayette, Littleton, and Fort Collins have adopted temporary moratoriums to study the issue further, according to Boulder Reporting Lab. That outlet also reported that Colorado currently has no statewide regulations specifically governing data center development, with state lawmakers expected to revisit the issue in 2027. Boulder County commissioners went further still, voting unanimously to prohibit data centers using more than 50 kilowatts of power in unincorporated parts of the county, limiting smaller facilities to industrial zones only.
Project Taurus Still Looms Over the City
Project Honey Badger isn't the only data center proposal that has stirred controversy in Colorado Springs. The city delayed a decision on the proposed west-side Project Taurus data center, with a new hearing date now set for just after the April 2027 city election, KOAA News 5 reported. That project, proposed by California-based developer Raeden for a former Intel microchip factory site on Garden of the Gods Road, would use around 50 megawatts and become the city's largest energy user by a substantial margin if approved, according to Colorado Public Radio.
Raeden's vice president has said the project would employ 60 to 100 people locally, mostly earning around $120,000, and a local economic development official estimated it could generate $119 million in sales taxes and $3 million in property taxes within its first 18 months, per the same outlet. But the proposal has also drawn significant public backlash — a meeting about Project Taurus in April 2026 drew so many concerned residents that organizers had to split it into two separate sessions, Colorado Public Radio reported.
The tension playing out in Colorado Springs reflects a national pattern. At least 36 utilities across the country have adopted large-load tariffs for customers such as data centers, according to The Colorado Sun. Gridwise Strategies has estimated that about 90 gigawatts of peak data-center demand requests will be filed nationally by 2030, even though only 65 gigawatts will actually be needed, the outlet reported — a gap that helps explain why cities like Colorado Springs are moving cautiously before saying yes to the next proposal.