A New Jersey appellate court has upheld the dismissal of a Cranford resident's lawsuit challenging the township's tax agreement for the 750 Walnut Avenue redevelopment, rejecting his fraud allegations and judicial-bias claims and finding no grounds to overturn the earlier ruling. William Thilly, who has fought the deal between Cranford and Hartz Mountain Industries for years, has now asked the New Jersey Supreme Court to take up the case.

According to TAPinto Cranford, the appellate court found no basis to overturn the dismissal of Thilly's suit over the township's tax agreement for the 750 Walnut Avenue site. The report notes that whether the state's highest court will actually hear Thilly's case remains undecided. Township Attorney Thomas Slattery reported on the appellate court's October 9 decision at a recent Township Committee meeting, saying the township expects to win on the merits if the Supreme Court agrees to take the case.

A Legal Fight That Started With the Original 2022 Deal

Thilly first challenged the township's original 2022 agreement with Hartz Mountain Industries, the same report states. After that first lawsuit was dismissed, he filed a second one, which he maintains raised new legal issues tied to an amended financial agreement reached later. Thilly wrote that his first action never challenged how New Jersey's Long Term Tax Exemption Law applied to this particular case, and he has continued to argue the amended agreement opened new legal ground.

Per the same account, Thilly argued the township inadequately evaluated the financial implications of the revised terms before approving them, and that the Township Committee should have reviewed the amended agreement's financial impact before voting on it. The Cranford Township Committee ultimately approved the amended agreement in October 2024 by a 4-1 vote, with Gina Black casting the lone vote against it. The amended agreement was part of a broader settlement between Cranford Township and Hartz Mountain Industries.

What the 750 Walnut Project Actually Includes

The redevelopment project at the center of the dispute includes 250 apartments, among them 38 affordable housing units, along with up to 250,000 square feet of commercial space, the report notes. Under a PILOT agreement, a qualifying redevelopment project makes negotiated municipal payments to the township instead of conventional property taxes — a structure permitted under New Jersey's Long Term Tax Exemption Law and intended to encourage redevelopment.

Thilly has claimed the 2024 amended PILOT agreement eliminated mandatory minimum annual developer payments to Cranford, and he has estimated the amended terms could mean $15 million to $20 million in lost revenue beyond the original agreement's estimated $85 million tax-revenue loss. The article is careful to note that Thilly's estimates have not been independently verified. The appellate decision reportedly found that a township financial consultant had identified opportunities to negotiate more favorable terms under the original agreement.

Township Says It Has Weathered Repeated Challenges

Slattery said Thilly has engaged the township in a series of lawsuits over the 750 Walnut financial agreement, and that the appellate court agreed the latest claims were barred as essentially repeated claims that also failed on the merits. For now, the case sits with the New Jersey Supreme Court, which must decide whether to hear Thilly's appeal — a decision the available record does not yet resolve.

The 750 Walnut site has a contentious history predating this legal fight. Back in 2019, Cranford's Planning Board rejected a request to rezone the property, a decision the Township Committee accepted at the time, according to Patch. That earlier dispute centered on a much larger proposal from Hartz Mountain Industries to build 905 apartment units on the site, a plan distinct from the smaller redevelopment later approved under the PILOT agreement now being litigated.