Construction crews are now working atop a warehouse at 19-05 Nevins Road in Fair Lawn, where Faropoint has broken ground on a 1.6-megawatt rooftop solar installation — the first piece of a much larger plan to put solar panels on 16 industrial rooftops across New Jersey. The remaining 15 projects, together expected to generate approximately 8.5 megawatts of capacity, have already been accepted into the state's community solar program, with nine cleared to begin construction.
The Hoboken-based industrial real estate firm announced the milestone on Nov. 4, according to NJBIZ, which reported that the New Jersey Community Solar Energy Program had formally accepted Faropoint's remaining projects and that nine had received notice to proceed — the regulatory green light that allows construction to move forward. ROI-NJ separately confirmed the Fair Lawn site as the first of the 16-project portfolio, putting its capacity at 1.6 megawatts.
Collectively, the 16 rooftop sites are expected to generate approximately 12.7 million kilowatt-hours of electricity annually, according to ROI-NJ's report, which also cited an estimate of roughly 8,500 metric tons of avoided carbon dioxide emissions each year. Outlets differ on how to translate that figure into household terms: NJBIZ put it at the annual electricity use of more than 1,700 homes, while ROI-NJ cited an equivalent of more than 2,000 homes.
Low-Income Access Requirements, With Differing Figures
Community solar programs are designed to let renters and homeowners who can't install their own panels subscribe to a shared system and receive bill credits. NJBIZ's report states that Faropoint will reserve at least half of each project's capacity for low- and moderate-income households, while Electrek described the state program's requirement as a minimum of 51 percent. Electrek's coverage also pegged the capacity of the 15 additional projects at about 8.5 megawatts.
Faropoint's push is being guided by SolarKal, the company's independent solar advisor, which the NJBIZ report says has advised Faropoint on dozens of projects across its broader portfolio — not limited to New Jersey. The two companies also have community solar projects underway in Illinois, New York and Maryland, according to the same report. SolarKal's services for Faropoint reportedly span financial analysis, competitive procurement, developer evaluation and ongoing project management, and the firm is also said to have helped Faropoint select developers positioned to use federal clean-energy incentives before they phase out.
A Program Straining Against Grid Capacity
The timing of Faropoint's rollout lands amid a broader statewide reckoning over whether New Jersey's grid can actually absorb the solar capacity being approved. A Dimension Energy analysis found that 400 megawatts of community solar projects statewide cannot connect to the grid because of capacity restraints, the same NJBIZ report noted. POLITICO's energy newsletter framed the same 400-megawatt figure differently, describing it as likely defunct community solar capacity — enough, by that outlet's estimate, to power about 80,000 homes.
POLITICO also reported that the most common reason community solar projects stall is competition from other solar developments trying to connect to the grid at the same substation. Citing a separate Dimension Energy analysis, the outlet reported that 91 projects totaling 125 megawatts had been accepted into the state Board of Public Utilities' community solar program in 2024 or earlier but still had not come online as of its reporting.
State Program Has Grown Sharply Since Spring
New Jersey's community solar ambitions expanded significantly this year. In March 2026, the state Board of Public Utilities approved a 3,000-megawatt expansion of the program, which NJBIZ described as the largest capacity allocation in state history. As of Sept. 30, the statewide community solar pipeline included 362 projects totaling 654,913 kilowatts, representing more than half of the overall pipeline capacity, per the same NJBIZ reporting. By comparison, the state had 251 installed community solar projects totaling 337,661 kilowatts at that point, according to figures attributed to the New Jersey Board of Public Utilities.
Whether that backlog clears before Faropoint's remaining rooftops come fully online remains an open question tied to the grid-capacity constraints documented across the state. For now, the Fair Lawn installation stands as the tangible first step in a portfolio that, on paper, could bring rooftop solar to more than a dozen additional New Jersey communities.