Blue Earth County has landed more than $21 million in federal money to tear down the badly damaged Rapidan Dam southwest of Mankato, more than two years after the structure partially failed during a punishing flood. The federal government announced it will provide the funding toward removing the dam, which sits about six miles from the city and stands roughly 87 feet tall.
FEMA said the money will support demolition of the dam, restoration of both Blue Earth River banks at the site, and construction of a parking area, as reported by the Minnesota Star Tribune. The full project is estimated to cost around $28 million, and according to mankatofreepress.com, FEMA's share covers about 75% of that total. Blue Earth County anticipates the state will pick up the remaining 25%, and the Star Tribune reports Minnesota is expected to contribute much of what's left.
Blue Earth County Administrator Josh Milow said the county had worked with FEMA for almost two years to secure the award, the Star Tribune reports. Milow also clarified that the funding is separate from the nearby County Road 9 bridge replacement, telling the paper that project's money came from the Federal Highway Administration instead — a bridge that was demolished in February 2026.
A Dam Built for Power That Hadn't Powered Anything in Years
The Rapidan Dam was originally built to supply electricity to Mankato, and when it first went up in 1910, it doubled the city's power system capacity, according to the Star Tribune's reporting. By the time catastrophic flooding hit in 2024, though, the dam had stopped providing any electricity to Mankato for years.
That flooding arrived on June 24, 2024, when the Blue Earth River overflowed and eroded the dam's west edge, cutting through the sandstone bluffs the structure was built on, per the Star Tribune. Logs and debris blocked five of the dam's steel gates, and officials said the structure should have been able to clear the water without that buildup — the blockage is what caused the partial failure, the paper reports.
The scale of the erosion was staggering: floodwaters scoured away an estimated 217,377 cubic meters of earth, enough to fill 87 Olympic swimming pools, according to the Star Tribune. The flooding also sent a house tumbling into the river and destroyed a local family's cafe, the Rapidan Dam Store, which has since relocated to downtown Mankato.
Why the County Chose Removal Over Repair
In 2024, the Blue Earth County Board voted to remove the dam rather than fix or replace it, arguing that keeping it standing would cost far more than tearing it down, the Star Tribune reports. Part of that calculus traces back to the site itself — the dam was built on erodible sandstone bedrock in a flood-prone area, a vulnerability that became impossible to ignore once the 2024 flood exposed it.
A federal report described by mprnews.org found that removing the dam would have a long-term beneficial effect on environmental resources. Public Works Director Ryan Thilges said the county hoped to be in position to advertise and award a removal contract in early 2027, pending sign-off from regulatory agencies.
Environmental Review Clears a Hurdle, Timeline Still in Flux
More recently, the Blue Earth County Planning Commission determined that a full environmental impact statement is not needed for the proposed removal, according to keyc.com. That decision was scheduled to go before county commissioners for final approval on Dec. 1. An earlier environmental study flagged by the same station noted the removal carries its own risks, including trapped sediment being released downstream and potentially hazardous materials like paint and asbestos at the site.
Milow told the Star Tribune he hopes Blue Earth County can begin the dam removal in summer 2027.
How the Cost Compares Nationally
Removal projects of this scale aren't unusual, even if the price tag sounds steep. A 2023 study compiled costs for 668 U.S. dams removed between 1965 and 2020, drawing on 455 sources, according to frontiersin.org. In 2020 dollars, those projects totaled $1.522 billion combined, with individual dam costs ranging from as little as $1,000 to as much as $268.8 million.
The same study found median removal costs of $157,000 for dams under 5 meters tall, $823,000 for dams between 5 and 10 meters, and $6.2 million for dams taller than 10 meters — the Rapidan Dam, at 87 feet, falls well above that top tier. Researchers identified dam height, average annual discharge and project complexity as the strongest cost drivers, a pattern that tracks with the scale of the work now planned for the Blue Earth River.