Folsom Dam Flood Project Could Halt in January as Federal Funding Stalls

AI Assisted Icon
Published on November 25, 2026
Folsom Dam Flood Project Could Halt in January as Federal Funding StallsFolsom Lake lies behind the dam, with the auxiliary spillway and access road to the right.
Quintin Soloviev / Wikimedia Commons, CC BY 4.0, cropped / Wikimedia Commons

A nearly $500 million effort to fortify Folsom Dam against catastrophic flooding could grind to a halt as soon as January, after the U.S. Army Corps of Engineers failed to secure additional federal funding it needed by the end of August. State flood officials say the agency now plans to stop construction, leaving most of the planned improvements unfinished and putting a project meant to protect more than 500,000 people in the Sacramento region in limbo.

The project, which began in 2019, calls for raising dikes and installing new top bulkheads on all eight of Folsom Dam's metal gates, according to CBS News. The gate modifications are designed to let each gate hold back an additional three feet of water during heavy rainfall, boosting the roughly 70-year-old dam's capacity during major winter storms. So far, only one of the eight gates has been modified.

Bulkheads for the remaining seven gates have already been manufactured and are sitting at the project site, waiting to be installed, the outlet's report notes. Todd Bernardy, a flood projects branch manager with the California Department of Water Resources, said the Corps needed additional funding by the end of August but did not receive it. “We don't want to see this project stopped. We don't want to see this project paused,” Bernardy said, per the same report.

Flood Officials Warn of Rising Costs and Lost Momentum

Flood officials say any delay in construction could add millions of dollars in costs, compounding the stakes of an already expensive undertaking. State flood officials reportedly raised concerns about the project's future at a hearing last month, underscoring how close the funding gap is to actually disrupting work at the dam.

Keeley Bosler, a member of the Central Valley Flood Protection Board, called the development troubling. Fellow board member Joseph Countryman went further, saying the project is the most important remaining on the American River and that stopping it after roughly $300 million has already been spent would leave it without its intended benefit — something he described as outrageous.

Flood Control Agency Pushes Washington for More Money

Jason Campbell, executive director of the Sacramento Area Flood Control Agency, said the project is critical to regional flood protection. He said his agency is working to persuade federal officials and lawmakers in Washington, D.C., to find additional funding and keep construction moving, framing the advocacy effort as essential to seeing the upgrades through to completion.

Folsom Dam helps protect communities along the American River from flooding, and one gate is currently out of service because of the ongoing construction. Despite the funding uncertainty, flood officials do not expect the construction work to affect flood control operations this winter.

A Project With a Shifting Timeline

The dam modification effort has seen its scope and schedule described differently over the years. A 2020 report from CapRadio described it as a $373 million Army Corps project, with $218 million coming from federal funding, and said all work should be completed by 2025 — a forecast that predates the current shortfall. That same report said the added height and storage were expected to give the facility 300-year flood protection.

By 2023, an Army Corps account published on DVIDS said the remaining seven dikes were targeted for completion in 2027. Neither timeline reflects the current funding standoff, which now threatens to pause work before the remaining seven gate bulkheads can be installed.