Denver/ Transportation & Infrastructure

Fort Laramie Canal Tunnel Rebuild Begins After Years of Planning

AI Assisted Icon
Published on November 20, 2026
Fort Laramie Canal Tunnel Rebuild Begins After Years of PlanningSource: CrowN / Unsplash

More than seven years after a tunnel collapse and canal breach disrupted water deliveries to farmland across Nebraska and Wyoming, crews have finally broken ground on a permanent fix. Officials marked the start of construction on Tuesday at an on-site launch event along the Fort Laramie Canal, celebrating a $150 million rebuild of the Goshen/Gering–Fort Laramie Canal tunnels that has been years in the making.

The project is a joint effort of the Goshen and Gering irrigation districts, according to the Lincoln Journal Star. Tunnel No. 2 collapsed in July 2019, and the resulting structural failure curtailed water deliveries to more than 107,000 acres in Nebraska and Wyoming, the paper reports. Permanent replacements have taken years to plan and fund.

Goshen Irrigation District president Shawn Booth thanked project participants as work began, the paper reports.

Why the Project Took So Long to Fund

Getting to this point required stitching together funding from multiple sources. The project’s funding includes state grants and federal support, according to the Journal Star. The Bureau of Reclamation is among the federal funding sources.

Funding and permitting have been part of the project’s multiyear development. The districts had an option to draw on a $58.5 million low-interest Reclamation loan. Wyoming State Sen. Cheri Steinmetz, who represents District 3, spoke at the ceremony. Additional support is still needed for the project.

The project's estimated cost is approximately $150 million, according to the Journal Star. An October 2025 update from the University of Nebraska–Lincoln Panhandle Research Extension and Education Center said the districts had an option to draw on a $58.5 million low-interest Reclamation loan.

Construction Timeline Stretches Into 2028

The first-stage work on Tunnel No. 2's inlet and outlet structures was completed by July 2026. Plans included building access roads and installing power lines for the heavy equipment needed on site, the Journal Star reports. Excavation on Tunnel No. 2 will continue through the fall and winter off-season. Tunnel No. 1's inlet and outlet structures are expected to be developed during fall 2026 and winter 2027.

Tunnel No. 1 excavation and replacement is slated to begin in fall 2027, with that portion expected to wrap up by spring 2028 — the same target set for completion of the overall project, according to the paper. The districts’ sequence puts Tunnel No. 2 first, followed by Tunnel No. 1 excavation in fall 2027. A separate account from The Fence Post similarly describes the first stage of replacing Tunnel No. 2, covering its inlet and outlet, as already completed.

A Scare With the Specialized Equipment

The project hit a snag last month when a transport accident on October 27 damaged the custom-built Segment Erector, a key piece of tunneling equipment, according to a release from the Goshen Irrigation District published by GoCoNow. The district described the equipment damage as significant.

The district said repair work was underway while the main digger-shield assembly continued. Separately, the release noted that Mountain View Building Inc. has been working on soil nailing and applying shotcrete to stabilize excavated slopes around the Tunnel 1 outlet.

The stakes of getting the rebuild right are underscored by how tight water delivery windows have become in the interim. The Fence Post reports that deliveries for the three main North Platte River Valley irrigation districts were expected to run just 30 to 40 days during the 2026 season, compared with an average delivery period of roughly 70 to 90 days — a gap that has left farmers watching the tunnel project's progress closely as the new construction season gets underway.