An 83-unit senior-living facility proposed for 4.46 acres of vacant land on the west side of Wagner Way in Gig Harbor is drawing pushback from neighbors worried about traffic, noise and a wetland area that a nearby preschool says is central to its outdoor classroom. The three-story building, with a daylight basement, would include 71 assisted-living units and 12 dedicated memory-care units, according to city permit records.

The project, proposed by Rush Commercial, a division of the Rush Companies, is referred to in permit filings as Mallard's Landing Lot 7, or Mallards 7. The Gig Harbor permit portal lists West Harbor Corporate Park LLC as the property owner, and that LLC is registered to Rush executives, per Washington state business records. Project narrative materials were first submitted in January 2019, with Rush resubmitting materials last year after making changes to address staff comments, the Tacoma News Tribune reported.

Mallards 7 sits across the street from the Lodge at Mallard's Landing, which offers independent living, assisted living, memory care and respite care. Rush Companies vice president Danny Kruse said the new project is not affiliated with that facility, which was sold in July 2026 to an LLC affiliated with Dallas-based Medcore Partners, according to the same report.

City Reviewing Multiple Permits, Hearing Set for December

Gig Harbor Community Development Director Eric Baker said the land-use permits under review include a conditional use permit, an alternative landscape plan, design review and major site plan review. The subdivision's binding site plan is being handled on a separate administrative track, Baker said, and building permits may be issued only after the land-use review is complete.

The Tacoma News Tribune reported that the city hearing examiner will hold an in-person and virtual hearing on the project at 1:30 p.m. on Dec. 1. A notice posted by the City of Gig Harbor gives that same date and time as the public hearing date, with the hearing to be held at the Gig Harbor Civic Center at 3510 Grandview Street. Baker said the project's timeline beyond that hearing is currently unknown.

Rush received a request from the News Tribune to confirm its status as the primary applicant and to provide an estimated construction and opening timeline, as well as to respond to public comments about traffic, noise, light and other impacts. Kruse told the outlet, “We don't have any comments at this time as we are working through the city's normal process.”

Neighbors Cite Ridge Homes, Speeding Concerns

Roughly 20 people have submitted written comments to the city on the latest plans since October, with most coming from the nearby Legacy neighborhood and its homeowners association, the report notes. The Legacy neighborhood includes 62 homes built around a small loop off 72nd Street, and nine of those homes sit on a ridge overlooking the project site.

Legacy HOA board president Steve Donovan said the association is concerned about the project's potential effects on nearby residents' quality of life, especially for those nine ridge homes, as well as light and noise from the proposed development. Legacy residents are also worried about speeding and traffic safety on Wagner Way, with drivers coming from Skansie Avenue tending to speed up 72nd Street toward Wagner Way, Donovan said. He added that his wife's car was totaled in a collision on Wagner Way on June 18.

Developers propose accessing the development via entrances onto 72nd Street and Wagner Way, according to the project's traffic analysis. An initial traffic impact analysis was completed in December 2018 and updated in May 2026; the updated version recommended adding a raised crosswalk with a flashing beacon at the intersection of 72nd Street and Wagner Way, along with striping, signage and vegetation clearing to improve visibility around the corner.

Donovan said Legacy residents would prefer a crosswalk at Teal Loop and 72nd Street, opposite Sinclair Avenue, arguing that location would serve a school bus stop and help families cross safely while also slowing traffic.

Preschool Says Wetland Is Core to Its Outdoor Learning

Curious by Nature Preschool operates a campus in a building on Wagner Way, and campus director Carlee Sutherland told the city that the wetland area at the project site “is the heart of our outdoor learning environment.” She said losing that habitat would harm both wildlife and the preschool community, and she asked the city to explain how staff evaluated impacts on the preschool's wetland use, pickup and drop-off routines, walking routes and construction safety.

City permit records indicate the site contains two wetlands designated as Category IV, which the News Tribune reports receive the least amount of protection under the state's rating system. The project proposal includes onsite stormwater detention, parking, landscaping and pedestrian paths connecting to frontage improvements on 72nd Street and Wagner Way, according to the public notice.

A design-review narrative filed with the City of Gig Harbor indicates the site sits within the RB-2 zoning district, where an assisted and independent-living facility is allowed through a conditional use permit. The proposed building would offer licensed assisted-living units and might also accommodate independent living depending on demand, according to the project materials.