Portland/ Politics & Govt

Hood River City Council Extends Data Center Pause Through 2027

AI Assisted Icon
Published on November 18, 2026
Hood River City Council Extends Data Center Pause Through 2027Oregon Department of Environmental Quality — State Data Center Permit Regulator
Google Street View

Hood River City Council extended its data-center moratorium through 2027, keeping a local pause in place after the version adopted in April was scheduled to expire at the end of this year. The new resolution puts the council's concerns about large-scale data centers back on the record, along with its support for responsible statewide regulation.

The Nov. 9 vote was unanimous. Councilor Doug Stepina moved the extension and Councilor Ben Mitchell seconded it, Columbia Gorge News reported. City Manager Abigail Elder had set out three choices that night: let the April moratorium expire, pass another resolution, or pursue a formal state moratorium. The council took the middle path.

A Signal With No Proposal Attached

Stepina said he wanted the vote to show that Hood River strongly opposed having a data center in the city. He also said he opposed leniency toward the facilities, given that they are already present in the surrounding area. The point was not abstract. Data centers are a regional industry, and the question in front of this council was whether Hood River would be an easy next stop.

Mayor Paul Blackburn credited Stepina with bringing the issue to the council. He said the state caught up after Hood River stated its position. Elder described the city as among the first to discuss a data-center moratorium, and said other communities have since passed similar resolutions or statements of concern.

Dan Kearns framed the same split as an investment problem. Data-center companies, he said, generally avoid places where they are not wanted, because the projects are large investments. The Dalles wants data centers, he said. Hood River has expressed that it does not.

The council that took the vote includes Anna Cavaleri, Ben Mitchell, Gladys Rivera, Paul Blackburn, Doug Stepina, Grant Polson and Amanda Goeke. Whatever individual members had argued before the motion, the extension itself did not split.

Why The Formal Option Fell Away

Elder's objection to a formal moratorium was more specific than a preference for softer language. She said that route would assume a reason the city cannot currently have data centers, and a desire to resolve that reason so the facilities could be allowed later. She said that was not what she heard from the council in April.

A formal instrument, in other words, would have treated opposition as a temporary defect in the code. The April discussion, as she recounted it, did not come with a plan to clear the way. Passing another resolution kept the objection intact without promising a future yes.

There was a live argument for stopping there. Some councilors and the mayor supported letting the April moratorium expire because of the statewide permitting pause. That position did not become the council's action. The resolution the council did pass establishes its concerns about large-scale data centers and its support for responsible regulation at the state level.

Rules The Code Does Not Yet Have

Hood River is updating its development code, and that code does not include policies or provisions tailored to data centers. The update had been scheduled for completion in fall 2026. Elder said it is taking longer than expected.

The original moratorium was built to run out at the end of 2026, the year the rewrite was supposed to land. Extending the pause through 2027 keeps a local position on the books while that work runs long. The city has received no large-scale data-center inquiries. A company that did show up would still be walking into a code written without rules for this use.

The meeting packet supplied the practical list behind the political one. Large-scale data centers, it said, raise concerns about electricity demand, water resources, infrastructure, utility rates and surrounding communities. Those are not side issues for a community considering a data center. They are potential costs for surrounding communities, whether or not an application has arrived.

Salem's Pause, And A City That Wanted The Opposite

Gov. Tina Kotek directed the Oregon Department of Environmental Quality to pause permit applications for new or expanding data centers until July 2027, OPB reported. The direction expanded an earlier moratorium that had paused data-center development on state-owned land. Hood River's resolution and the state's permit freeze are different tools. They now run alongside each other well into next year, on deadlines that do not match.

An OPB-commissioned poll found nearly two-thirds of likely Oregon voters favored a temporary ban on data centers. The Legislature is expected to address data-center regulations after it convenes in January. Hood River's extension will still be in effect when that session opens, which is part of what a through-2027 resolution buys a city that wants Salem, not just City Hall, to write the rules.

Umatilla heard the same gubernatorial pause as a threat to money already in the local picture. Its city council voted to declare an emergency "due to the threat of widespread financial loss," OPB reported. Staff estimated the city would lose out on more than $2.5 million in annual tax payments and $12 million in water-infrastructure improvements. Hood River is extending a pause over an industry that has not brought it a large-scale inquiry. Umatilla is counting tax payments and water work it expected those facilities to fund.

Shorter Clocks Down The Valley

Other jurisdictions are using much shorter freezes, often as a bridge to new text. A 120-day data-center moratorium took effect Oct. 22 in Clackamas County unless it is extended, KATU reported. On Nov. 4, Oregon City commissioners approved their own 120-day moratorium on data-center and battery-energy-storage development. It blocks applications in five industrial and mixed-use zones while staff audit the code and draft regulations. Oregon City had no open data-center applications or inquiries when it acted.

Hillsboro has already moved from waiting to zoning. In October the council unanimously approved rules that establish where data centers and energy-storage facilities can operate and how they must seek approval, OregonLive reported. A second phase is aimed at building standards and environmental requirements. That is a city deciding the terms of entry. Hood River, so far, has decided it does not want the knock.

The local extension runs through 2027. The state's permitting pause runs until July. The development-code update that was scheduled for this fall is still the unfinished piece Elder flagged. Between those dates, the position on Hood River's books is the one Stepina asked the council to make obvious: strong opposition to a data center in the city, and no leniency borrowed from the facilities already sitting nearby.