The I-78 Toll Bridge spanning the Delaware River is finally getting a fresh coat of paint after 37 years, with the Delaware River Joint Toll Bridge Commission awarding more than $13 million in contracts to overhaul the span's steel superstructure and tackle a list of deck and substructure repairs. Preparation work is set to begin in January, with completion targeted for the end of 2027 if the project proceeds as planned.
Commission members approved the contracts at their monthly meeting last Monday in Lower Makefield, Pennsylvania, according to WRNJ Radio. The painting and repair contract went to Anselmi & DeCicco, Inc. of Maplewood, New Jersey, for a not-to-exceed amount of $11,655,265, while STV, Inc. of Lawrenceville, New Jersey, landed the construction management and inspection contract for a not-to-exceed $1,553,970.31, per a Commission announcement.
The project traces back to deficiencies flagged in the Commission's 2025 Annual Maintenance Report and confirmed during subsequent field inspections, the announcement notes. It will mark the first time the bridge has been repainted since it opened on Nov. 21, 1989 — meaning the steel superstructure has been wearing its original paint job for nearly four decades.
What the Repair Work Covers
At the center of the project is cleaning and painting the seven-span twin bridge steel superstructures over the Delaware River, along with steel repairs where necessary, the Commission's report states. Crews are also expected to replace drain troughs at the river bridge's abutments and repair cracks and deteriorated concrete, or spalls, on both the river and approach bridge decks and substructures.
The scope extends further than just the river crossing itself. Work will include applying epoxy waterproof coatings on bridge seats throughout the Commission's I-78 jurisdiction, resetting rocker bearings where necessary on the river bridge and its approaches, repairing deteriorated slopes along I-78 roadway segments, and resealing deck joints across the corridor.
Timeline and Traffic Impact
Project preparation activities are anticipated to begin in January, with cleaning and painting to follow and drainage-related tasks scheduled for later in the project, the Commission's account explains. Motorists should anticipate a series of lane and shoulder closures throughout the project, though the Commission has said it will announce specific travel-impact details as they become available next year.
The bridge is the Commission's most heavily traveled river crossing, connecting North Jersey port facilities with warehouses in Pennsylvania's Lehigh Valley and areas farther south, west and north. The river bridge and its approaches carried 66,000 vehicles in 2025, underscoring how much freight and commuter traffic relies on the span.
With contracts awarded and a January start date approaching, the repainting effort is set to begin preparation activities in the new year. Whether the project stays on track for a 2027 finish will depend on how the work unfolds once crews begin preparation activities.