A Natchitoches, Louisiana construction firm has been awarded a multimillion-dollar federal contract to repair storm-battered foreshore dikes along Lake Pontchartrain in Jefferson Parish, with crews expected to begin work next month. The project targets erosion damage along more than six miles of flood-risk reduction features stretching from Kenner to Metairie, work that officials say is necessary to keep the area's storm defenses intact.

The U.S. Army Corps of Engineers New Orleans District awarded the construction contract to TKTMJ, Inc., according to DredgeWire. The contract's total award amount is listed at $53,254,517, per DredgeWire's reporting, while a separate federal contract brief from Aerotech News describes a $42,398,851 firm-fixed-price contract awarded to the same Natchitoches firm. Both accounts agree that $42,398,851 in federal funds was obligated at the time of the award, with DredgeWire specifying that figure covers work to complete reaches 1 and 3.

Where the Repairs Will Happen

The repair work will take place along the west side of Lake Pontchartrain, running from east of the West Return Canal in Kenner to the west side of the Causeway Bridge in Metairie, per the DredgeWire report. The job extends approximately seven miles and is part of the Lake Pontchartrain and Vicinity, Louisiana-Foreshore Dike Repairs under the PL 84-99 rehabilitation program, the outlet notes. The contract addresses erosion along reaches 1 through 4 of Jefferson Parish's lakefront flood risk reduction features.

Per the Aerotech News brief, Bids were solicited via the internet with four received before TKTMJ was selected. The contract scope laid out in that report includes construction access to the work site, demolition, clearing and grubbing, excavation and embankment placement, geotextile and stone placement, and turf establishment and maintenance. The same report lists an estimated completion date of November 15, 2027, while DredgeWire's account describes the project work as expected to be completed in winter 2027.

Fixing Damage From Zeta and Ida

The foreshore repairs will address damage from Hurricane Zeta in 2020 and Hurricane Ida in 2021, according to DredgeWire. Crews plan to add fill material, restore rock, and add stone splash padding as part of the effort to restore resiliency against wave overtopping and erosion along the shoreline.

The Lake Pontchartrain and Vicinity project provides coastal storm risk management for the greater New Orleans area on the east bank of the Mississippi River and is part of the broader Hurricane and Storm Damage Risk Reduction System, DredgeWire reports. One project feature includes a wave berm extension designed to reduce wave heights and runup so the structure can achieve the adjacent levee's design height, with the overall project intended to provide the 1% level of authorized risk reduction.

What Officials Are Saying

Col. Scotty Autin said past storms eroded foreshore features originally constructed by the Army Corps of Engineers, and that repairs are necessary to help ensure continued risk reduction, according to DredgeWire's account. Autin also said the Corps focuses many of its efforts on projects like this one to continue providing risk reduction for Jefferson Parish and the greater New Orleans area.

Project work is expected to begin in December 2026. Once construction starts, the bike path along the levee will be closed intermittently, and signs and barricades will be put in place when certain sections of the path are shut down, DredgeWire notes.

The TKTMJ award follows a procurement process that stretched back to earlier this year. A March 2026 notice seeking information from construction firms for preliminary planning estimated the project's value between $25 million and $100 million, according to SweetSpotGov. TKTMJ has also been active on other Louisiana storm-damage repair work; the firm submitted a $50,233,000 bid for separate Hurricane Ida breakwater repairs near Grand Isle, according to Citizen Portal.