Crews are clearing trees and undergrowth next to Johns Island Park this month, the first visible step toward a long-promised recreation and aquatic center that residents have been waiting more than a year to see take shape. The work began early in November, and officials expect it to wrap up around Thanksgiving, setting the stage for construction crews to start leveling the land for the center's foundation.
The clearing effort comes after more than a year of planning and is meant to help construction start on time, according to Live 5 News. There's a hard deadline built into the schedule: crews must finish clearing the site by mid-December, after which all tree removal work has to stop to protect the endangered northern long-eared bat, per the station's report.
What's Actually Getting Built
Once finished, the new facility will measure more than 50,000 square feet, with Live 5 News reporting it will include a 25-meter by 25-meter pool, a gymnasium and a fitness room. The Post and Courier has offered a more detailed breakdown, describing a roughly 54,000-square-foot center with a 25-meter pool, a therapy pool, two full-sized high school basketball courts, two full-sized volleyball courts, four indoor pickleball courts and a yoga studio, according to The Post and Courier.
The pool's exact dimensions remain a bit murky across sources. While Live 5 News reports a 25-meter by 25-meter pool, a City of Charleston newsflash describes an indoor pool measuring 25 meters by 25 yards, according to the City of Charleston. The Post and Courier's reporting also notes that about 4,500 square feet of the building will be dedicated to three separate meeting rooms, and District 3 Council member Jim McBride has said the center might include classroom space as well.
Why Johns Island Has Been Waiting
McBride has described a long-standing gap in options for the island's residents. There's a clear dearth of recreation facilities or even fields on Johns Island, whether run by the city or the county, he told the same outlet, adding that the island's population has doubled over the past decade. Without a facility like the one now planned, residents who want to play pickleball or pickup basketball have had to leave the island and face traffic to reach other amenities, the station's report notes.
McBride has pointed to a similar gap on the aquatic side, saying there is no nearby pool in the area for residents to use. He's framed the project's value in practical terms, saying nearby amenities help people stay on the island and avoid driving elsewhere, and has said the recreation center will add a lot to Johns Island.
Funding and What Comes Next
The project carries a reported price tag of $65 million, funded through a $70 million bond referendum that voters approved in 2023, per the same Post and Courier account. It's a scale of investment with a local precedent: North Charleston recently spent $25 million on a similar facility in Park Circle that included a gymnasium and a 25-meter competitive swimming pool, according to an earlier Post and Courier report.
Once the tree removal is complete, construction crews will begin leveling the land to create the center's foundation, Live 5 News reports. Project leaders expect to break ground in early 2027, putting Johns Island on track for its first facility of this kind — assuming the bat-driven December deadline and the rest of the schedule hold.