St. Louis/ Transportation & Infrastructure

Kirkwood Train Station Still Unfinished as City Labels Contractor Unsatisfactory

AI Assisted Icon
Published on November 16, 2026
Kirkwood Train Station Still Unfinished as City Labels Contractor UnsatisfactoryKirkwood Train Station — Amtrak Stop Affected By Delays
Google Street View

Kirkwood's 1893 train station still isn't ready for passengers nearly two months after officials cut the ribbon on its renovation, and city staff say the contractor behind the delays has racked up nearly $700,000 in cost overruns. The historic depot at 110 W. Argonne Drive was supposed to be substantially finished months ago, but as of mid-November it remains closed, with occupancy now pushed to December at the earliest.

The renovation, which Kirkwood says began construction in late February 2025, was pitched as a roughly year-long project when it broke ground, according to Webster-Kirkwood Times. City leaders held a ribbon-cutting ceremony in mid-September, but even then, officials acknowledged at least a month of additional work remained before the station's interior would be ready to serve passengers, per the same publication's earlier coverage of the event. Two months later, that timeline has slipped further, with the renovation still incomplete.

City staff have pointed to Raineri Construction, the St. Louis-based contractor on the job, as the source of the holdup. Richard Holesinger said staff documented unsatisfactory performance of contract requirements, and he noted that staff had also run into issues with Raineri on an earlier Geyer Road project, the Times reports.

Nearly $700,000 in Overruns, With Contractor Possibly on the Hook

Information provided to the City Council puts delay-related cost overruns at $698,400, and the same information indicates Raineri Construction may be liable for at least part of that total — though no final liability determination has been reported. Kirkwood's construction management firm, Brentwood-based Navigate Building Solutions, has also requested an additional $119,307 to continue overseeing the project through December 30, according to the report.

City staff now expect the work to wrap up later this month, with occupancy potentially beginning in December. Jessica Winter said Monday that Kirkwood is meeting with the contractor, design consultant and owner's representative to hash out occupancy requirements, outstanding change orders and a firm substantial completion date, the station's report notes.

Cost Figures Differ Across Reports

Exactly how much the renovation costs has been described differently in local coverage. The Webster-Kirkwood Times' latest report pegs it as a $5.7 million project, while a September photo caption in the St. Louis Post-Dispatch described the station as nearing completion of a $4.7 million renovation and restoration. That same Post-Dispatch report, published in September, said the station was set to reopen the following week after a year of renovations — a timeline that has since proven optimistic.

The scope of the work has been consistent across reports, even if the price tag hasn't: the project includes exterior restoration and interior reconfiguration, a new slate roof with copper flashing, a new storage building, larger accessible bathrooms, and a geothermal heating and cooling system, according to the Times. State and federal grants are funding the majority of the budget, with more than $4.2 million in grant funding cited in that coverage, and a local citizens' group raised $1 million in donations before work began. At groundbreaking, Kirkwood officials called the renovation largely self-funded.

A Busy Stop Running Out of a Temporary Station

Kirkwood has owned the train station since 2003 and operates the local Amtrak stop with entirely volunteer staff — volunteers who, for now, are working out of a nearby temporary station while the historic depot remains closed. The stop is one of Missouri's busiest passenger rail stops, and it has emerged as the second-busiest stop on the Missouri River Runner line since two daily trains were restored to the route, per the Times' earlier reporting. Roughly 56,000 passengers used the Kirkwood station between September 2023 and September 2024, according to Amtrak figures cited by the paper, and some 46 volunteers work to keep the stop staffed whenever trains pull in.

Separately, the station's rail platforms and crossings are slated for a multi-million-dollar upgrade through a federal Amtrak program, with that work hoped to begin in spring 2027. An earlier bid report from the Post-Dispatch noted that Raineri Construction submitted the lowest cost of two bids for the station renovation project, while a Times report from when construction began said the restoration was expected to take at least a year to complete. A separate reader letter responding to the paper's coverage years earlier had pegged an estimated restoration cost at $4.6 million, underscoring how long cost estimates for the depot have fluctuated before the current overruns were disclosed.