Lawrence Kicks Off Mass Street Overhaul, Protected Bike Lanes Coming by 2027

AI Assisted Icon
Published on November 22, 2026
Lawrence Kicks Off Mass Street Overhaul, Protected Bike Lanes Coming by 2027Massachusetts St & E 23rd St — Reported Site of Right-Turn Lane Removal
Google Street View

Drivers and cyclists along Massachusetts Street between 14th and 23rd streets will start seeing utility crews in the roadway this week, as the City of Lawrence begins groundwork for a long-planned redesign that will narrow the corridor from four lanes to three and add physically protected bike lanes on both sides of the street. Construction itself is scheduled to start in December and continue into 2027, according to a city news release.

Utility Crews Move In First

Per the city news release cited by The Lawrence Times, utility companies may have workers out in the street ahead of the main construction push, and the city is advising drivers to follow posted signage and use caution around the work zones. The city has not provided a more specific construction end date beyond saying the project will run into 2027, and officials say they will share more details on closures, lane reductions and construction phasing as work progresses.

The Massachusetts Street Multimodal Improvements Project covers the stretch of Massachusetts Street from 14th Street to 23rd Street in Lawrence, Kansas. The city has described the overhaul as an effort to improve safety and mobility for people walking, biking, driving and using transit, and officials characterized the improvements as designed to create a safer, more accessible corridor that strengthens connections for all types of transportation, per the city's release.

Four Lanes Down to Three, With Protection for Cyclists

The redesign itself isn't new. The Lawrence City Commission approved a design for the project in December 2024. The project had a $494,915 design agreement. The design calls for converting the street from four lanes to three while adding on-street bicycle lanes with physical protection, rather than simple painted lanes. The project received about $2.3 million through a Transportation Alternatives grant.

The project’s construction funding combines a $2.376 million federal Transportation Alternatives award with $1 million in federal Carbon Reduction Program funds. That $3.376 million covers up to 80% of construction costs; the city estimated construction at $6.1 million, leaving a projected $2.724 million local share. The funding breakdown is detailed in the city’s 2025 agreement with KDOT.

City staff at that 2024 meeting also said all existing street parking would remain along the corridor, based on feedback gathered through community engagement. Lawrence's design includes median-separated bike lanes.

The protected-lane design was selected in part to accommodate the corridor’s many driveways and routine city operations. Commissioners chose a design with wider physical medians, which staff said would allow solid-waste collection while maintaining separation between cyclists and traffic; the city also weighed maintenance, snow removal and sweeping needs. Those operational concerns shaped the choice between several layouts, including a two-way cycle track, as shown in the project’s design history.

New Crossings, Signals and Intersection Changes

Beyond the lane reconfiguration, the project will bring a string of changes to how people cross and move along the corridor, per the city's release. The high-speed westbound right-turn lane at 23rd and Massachusetts streets will be removed, and a protected intersection is planned for 19th and Massachusetts streets. The 17th Street traffic signal will be replaced with a pedestrian-activated signal, and two mid-block pedestrian crossings will be installed featuring flashing beacons and refuge islands.

The redesign addresses a corridor that the city’s bike-plan safety analysis identifies as a concern: stretches of Massachusetts Street overlap with areas rated less comfortable for biking and with the Vulnerable Road User High Injury Network. The analysis found that four miles of Lawrence roads made up that network, where 30% of fatal and serious-injury crashes involving vulnerable road users occurred on just 1% of roadways. The figures are drawn from crash data spanning 2013–2023 in the Lawrence Bike Plan safety report.

The project will also fix sidewalks and ADA-accessible ramps along the route and add passenger loading and unloading areas to transit stops, according to the release. City officials have said street trees along the corridor will be preserved without widening Massachusetts Street itself. The project received an update in 2025, though the most recent detailed public timeline tied to construction comes from this week's city announcement.