Leland is moving toward construction on its first pedestrian crossing of U.S. 17, a signalized crosswalk near Ploof Road and Olde Waterford Way. The project has been years in the making.
The crossing would be built at or near the intersection of U.S. 17, Ploof Road and Olde Waterford Way, according to Town of Leland Resolution R-23-056. The project is a partnership between the Town, the Wilmington Urban Area Metropolitan Planning Organization and the North Carolina Department of Transportation, and would give Brunswick County its first pedestrian crossing of U.S. 17, according to the Independent Tribune.
Design plans call for a signalized, at-grade crossing paired with new sidewalk connecting into the existing Waterford-area network. The Town's own project page describes approximately 300 feet of new sidewalk on the northeast side of Olde Waterford Way. The Town has said the crossing and sidewalk would create the only pedestrian crossing across the multi-lane highway and connect pedestrian facilities on both sides, according to Leland's FY25-26 budget document.
How the Project Is Funded
The Wilmington Urban Area Metropolitan Planning Organization voted in October 2022 to allocate $666,623 in federal funds for the project's design, permitting and construction, with the Town committing a 20% match of $166,656 toward an estimated total cost of $833,279, per the resolution.
Under the terms of the federal funding agreement, Leland has five years from the authorization date of the funds to complete the initial work phase, unless a supplemental agreement grants more time, according to the resolution and project agreement on file with the Town.
Timeline Has Shifted More Than Once
Exactly when shovels will hit the ground has proven to be a moving target. A StarNews Online report from December 2024 said construction was scheduled to begin in the spring of 2026. The Town's construction bid documents set a bid deadline of Thursday, November 19, 2026, at 3 p.m. local time.
A History of Crashes at the Crossing Site
The project would add a dedicated pedestrian crossing near the U.S. 17 and Ploof Road intersection.
A separate NCDOT safety-study evaluation found that crashes at four U.S. 17 intersections in Leland, including Ploof Road, rose nearly 24% overall — from 161 crashes before safety improvements were installed to nearly 200 over the following nine years, according to WWAY. NCDOT attributed part of that increase to rising traffic volumes. At the same time, the agency said reflective signal backplates installed at the eastbound U.S. 17 red light at Ploof Road in 2021 were associated with a 25% reduction in targeted frontal-impact crashes there, with the crash-severity rating at that specific location falling by nearly half.
Community Priorities and What Comes Next
Public commenters have also raised concerns about workers, shoppers and residents crossing the highway without dedicated pedestrian facilities, according to the same report.
Per NCDOT, future crossing projects elsewhere will depend on existing project funding, identified needs, available funding and successful applications by local governments and planning organizations, the Independent Tribune reported, citing NCDOT's Veronica Scott. The outlet also reported that a construction funding request for the Leland project was still awaiting NCDOT authorization, even as the Town's updated final design plans, specifications and estimate had been approved by NCDOT.