MassDOT has published a conceptual planning study laying out how the state might finally stitch together three stubborn gaps in the Mass Central Rail Trail, a proposed 104-mile greenway stretching from Boston to Northampton. The options range from a relatively modest $13.1 million path through Hardwick to a Clinton bridge alternative that could run as high as $170 million. About 72 miles of the trail are already open, but the remaining disconnected stretches have long frustrated planners trying to link the eastern and western halves of the state.
Three Gaps, Three Very Different Problems
As Streetsblog Massachusetts reports, the new study examines a 4.9-mile segment between Belchertown and Palmer, a 1.4-mile stretch near Gilbertville in Hardwick, and a short but technically brutal crossing of the Nashua River gorge in Clinton. MassDOT commissioned a high-level feasibility study of the full corridor back in 2021, and this latest conceptual study digs deeper into the three toughest remaining links. Completing the trail would require new river crossings, significant infrastructure investment, land acquisition, and political will, according to the outlet's reporting.
The Belchertown-to-Palmer gap runs from Springfield Road in Belchertown to Griffin Street in Palmer, and the historic railroad right-of-way there is described as generally intact and already used as a trail in parts, with the Town of Belchertown owning most of the existing path. The report characterizes this as the least complicated of the three gaps and the one most likely to get built first.
A Missing Bridge Over the Swift River
The Swift River forms the boundary between Belchertown and Palmer, and while the old railroad bridge over it is long gone, the original abutments still stand on both banks. MassDOT's study says the crossing could require either one large bridge span or a combination of smaller bridges and boardwalks threading through a river peninsula, potentially stretching more than 525 feet. Further east, the corridor between Franklin Street and Shea Street remains intact and undeveloped but is privately owned and posted with no-trespassing signs, prompting the study to recommend acquiring that private land.
MassDOT pegs the Springfield Street-to-Franklin Street segment at around $16.7 million, while the Swift River bridge and the land acquisition east of Franklin Street would add another $92 million, per the same study. On a smaller scale within this gap, the Jabish Brook crossing still has an old wooden trestle bridge; if it cannot be rehabilitated, the study proposes an 80-foot pedestrian bridge with new abutments and approaches. The Town of Belchertown has already secured MassTrails grant funding to begin rehabilitating that bridge with a new deck, and the segment's northwestern end connects to Piper Farm, a town conservation area. A separately funded 1.2-mile Maple Street trail extension is slated for construction by 2031.
Hardwick's Detour Around Lost Rail Bed
In Hardwick, the former railroad right-of-way has been swallowed by suburban development, so the recommended route instead follows a new separated shared-use path along State Route 32, a MassDOT-controlled roadway, plus new sidewalks on River Run, a low-traffic residential street. The segment would run from the existing East Quabbin Land Trust trailhead on the outskirts of Gilbertville to Creamery Road near the Barre town line, ultimately knitting together two existing trail segments into a continuous five-mile route along the Ware River. The East Quabbin Land Trust has already built several of those existing pieces. MassDOT estimates this segment would cost $13.1 million to construct.
Clinton's Gorge Forces a Costly Choice
The Nashua River gorge gap in Clinton, located in Worcester County, is the shortest of the three gaps by distance but by far the most complicated, and the study labels it a complex project with high implementation difficulty. The old Mass Central Railroad trestle that once crossed the gorge stood 100 feet above the river, and the site now contends with a large dam, steep slopes, multiple roadway crossings, utility corridors, and potential environmental impacts to ponds and conservation land.
One option under consideration would rebuild something close to the original railway route: a 1,000-foot bridge spanning the gorge, which MassDOT estimates would cost about $170 million but would offer a simple trail route avoiding steep climbs and an at-grade crossing of Boylston Street, a busy state highway. The alternative is a ground-level trail that zig-zags across the gorge with multiple switchbacks to negotiate a 100-foot elevation change. The study's lowest-cost ground-level alternative would follow existing roadways, including River Street along Lancaster Mill Pond — a paved road currently gated to motor vehicle traffic at Boylston Street. These cheaper ground-level options carry lower price tags but would require embankments on steep slopes and could affect nearby waterways and conservation lands.
Clinton's rail-trail ambitions predate this study. The town purchased its section of the corridor from the Boston & Maine Railroad back in December 2020, according to the Clinton Greenway Conservation Trust. That stretch includes a 1,110-foot tunnel that a pre-acquisition inspection found suitable for a shared-use path after remediation, plus a section along the Wachusett Reservoir watershed. The relocated rail bed there once required a separate 917-foot trestle bridge standing 133 feet above the Nashua River. In June 2022, the trust received a MassTrails grant, matched by the town, to fund design work including the tunnel remediation.
What Finishing the Trail Could Mean
The case for pushing through these costly gaps rests partly on numbers from a 2023 analysis, which found that completing the full trail network could generate more than $200 million a year in economic activity from trail-oriented tourism, according to the same Streetsblog Massachusetts report from that year. That study projected a continuous off-street connection could draw between 4 and 5.5 million visitors annually and save $6 million to $7.7 million a year in reduced health-care costs for trail users. For comparison, a 2021 study of the Great Allegheny Passage found that trail generated $121 million in additional tourism-related spending.
Elsewhere along the corridor, one-mile segments in Belmont and Wayland are also moving toward construction, part of the broader patchwork of projects needed to eventually link Boston to Northampton. For now, the Belchertown-to-Palmer gap appears closest to a realistic path forward, while Clinton's gorge remains the trail's most expensive and technically demanding puzzle to solve.