Microsoft Files Tyrone Data Center Site Plans as Church, Homeowners Push Back950 Senoia Rd. — Tyrone Town Council Project Hearing
Google Street View

Microsoft has submitted its formal site plans for the incoming data center in Tyrone, Georgia, kicking off a technical review process that town officials say could stretch roughly 69 days before it wraps up. Tyrone officials informed residents of the submission, and the filing arrives as neighbors — including leaders tied to a nearby Catholic parish and a homeowners' association outside town limits — continue pressing officials over noise, environmental and property concerns tied to the project.

According to Fayette County News, technical review coordination has now begun on Microsoft's submission, and Tyrone officials must return first-round review comments to the company by the first week of December. That first round alone is expected to take at least a month, and the outlet reports the suggested overall timeline for the full site-plan review is about 69 days. Town staff separately confirmed to Citizen Portal that the submitted site plan is now under technical review.

The project itself was approved by the Tyrone Town Council in March 2024, according to the Town of Tyrone's own data center information page. Per the station's report on site plans, the council would only re-enter the picture if Microsoft later seeks substantive changes to its original development plan — meaning the current filing does not require a fresh council vote. Planning commission approval is still required for a couple of items tied to the development, though the council itself will not make further approval decisions on the project; it will instead receive status updates from Tyrone staffer Phillip Trocquet, who has said he plans to keep members informed throughout the process.

Project Size Figures Don't Match Across Documents

How big the data center will actually be remains murky depending on which document is cited. Fayette County News has reported the planned site spans 161 acres, with about 147 acres inside Tyrone town limits and the rest in Fulton County. Data Center Dynamics has described the project as two buildings totaling 500,000 square feet, while the same account relayed by Citizen Portal says subsequent development-of-regional-impact documents consistently evaluated a two-building, 504,600-square-foot project — matching the figure the council approved in 2024. That same Citizen Portal report notes one field on the initial state DRI form listed the project at 1,500,000 square feet, a discrepancy the available record does not resolve.

Town staff have said they will ask Microsoft questions about its proposed cooling system specifically to help pin down expected water and sewage usage, per the same account. Councilmembers have also asked staff how the town intends to verify that Microsoft sticks to its original proposal as the project moves through permitting. Once the site-plan process concludes, Microsoft must still obtain a land-disturbance permit before it can begin any vertical building construction.

Noise and Lighting Rules Still Being Written

Tyrone is simultaneously updating its noise and light ordinances, which are currently in legal review, Trocquet has said he hopes feedback on those draft rules may return to council sometime in December. Town officials maintain the ordinance work remains relevant even with Microsoft's site plan already filed, since some provisions tied to health, safety and welfare — including noise and light standards — can still apply even though broader ordinances generally cannot take effect retroactively against an application or permit already issued.

Church and Out-of-Town Neighbors Voice Opposition

At a Tyrone council meeting earlier this month, seven individuals spoke in opposition to the data center, with public commenters raising concerns about potential environmental and homeowner impacts. Among them was Mike Anderson, who represented Father Valery Akoh, pastor of St. Matthew's Catholic Church, telling the council his comments reflected concerns shared by many members of the faith community. Anderson's remarks are being reviewed by the Bishop of the Archdiocese of Atlanta, and the proposed data center would sit around two of the four sides of the church's property.

Jay Horn, president of the Foxwood homeowners' association in neighboring Fairburn, also addressed the council despite not being a Tyrone resident himself. Horn, who lives about 4.3 miles from the proposed site, said the overall effects of the data center are not yet known, and that Foxwood residents oppose the project because it affects them even though they live outside Tyrone town limits. Broader public comment has also focused on environmental impacts, utility usage, and effects on property owners, according to Fayette County News, with residents requesting independent third-party studies and a moratorium on future data center projects in Tyrone, a request raised by Citizen Portal as well. The Tyrone council currently has no further scheduled input sessions specifically on the data-center development, leaving the technical review — and the ordinance process running alongside it — as the venues where these concerns will next be addressed.