Mountainside's library was already closed for roof repairs when an underground electrical fire knocked out its power on October 7, according to a council resolution, and now its reopening hinges on when PSE&G shows up to make the final connection. The Borough Council voted 4-0 on November 24 to approve up to $68,700 for emergency replacement of the library's underground electrical service, a cost separate from the roof project that has kept the building shut since early September.
The library had already been scheduled to close from September 7 through November 30 for the start of a roof replacement, a timeline the borough laid out in a notice posted to Mountainside's borough website, which said the shutdown was necessary to ensure the safety of the public while the initial phase of roof construction was underway and pointed to a reopening date of December 1. As reported by TAPinto Mountainside, that timeline has since been complicated by the fire, which left the library without power according to the council resolution, and the building currently has no electrical power, per the borough's DPW director.
Electrical Work Finished, Final Hookup Still Pending
Resolution 139-2026 requires the library to reimburse the borough $55,000 for the emergency work, the same TAPinto Mountainside report notes. The library has since replaced all electrical lines to the building and thanked the Mountainside Department of Public Works for helping complete the electrical work, according to a library update cited in the article. What remains outstanding is PSE&G making the library's final electrical connection, with no timing yet available for when that will happen.
The roof project itself has been underway for months. The borough's roof replacement and repair contract traces back to April 21, when the Borough Council approved a $682,958 contract with Mak Group LLC of Saddle Brook, according to a local blog's reporting. That contract combined a $627,758 base bid with a $55,200 alternate recommended by the Borough Engineer. Five contractors had submitted bids back on March 3, with the next-lowest base bid coming in at $878,000 and the highest at $1,182,000, the same blog post detailed.
Water Leaks and Carpentry Forced Furniture and Books Out
Because of roof-project water leaks and interior carpentry work, the library moved furniture and thousands of books out of the building, per the TAPinto Mountainside account. The library is completing roof work and related interior repairs, but it still needs a thorough cleaning before any of that furniture and those books can be returned. Once that happens, the library estimates returns may take a week or more to appear on patrons' accounts.
In the meantime, the library is accepting book returns through the slot left of the front door. Patrons with questions can email the library at [email protected].
Where Mountainside Cardholders Can Borrow In the Meantime
Mountainside patrons aren't without options while the building sits dark. Cardholders can place holds and pick up materials at Pillar network locations including Summit, New Providence and Berkeley Heights, and they can borrow DVDs and Blu-rays at those same Pillar locations, a network that includes more than 50 locations in all. Patrons can also access e-books, audiobooks, streamed movies and magazines from home through Libby, Hoopla and Kanopy.
Beyond the Pillar network, Mountainside patrons can borrow in person at other Union County libraries and most Middlesex County libraries, though patrons at libraries outside Pillar cannot place holds there — they can only borrow items already on the shelf. That lines up with earlier guidance reported by the local blog, which noted Mountainside cardholders have access to the Middlesex-Union Reciprocal Agreement network, naming Westfield, Berkeley Heights and Cranford as the closest options.