St. Louis/ Politics & Govt

NAACP Says Lambert Airport Skipped Bidding on $17 Million in Emergency Work

AI Assisted Icon
Published on November 19, 2026
NAACP Says Lambert Airport Skipped Bidding on $17 Million in Emergency WorkSource: Bohao Zhao / Wikimedia Commons

The NAACP of St. Louis says Lambert Airport has been quietly approving emergency construction contracts worth millions of dollars without ever opening them up to public bidding, and the chapter wants the city to release records proving otherwise. Leaders say the Board of Public Service signed off on the work with no public bid opening, and they are now demanding that two audits requested a few weeks ago finally be made public.

Two Projects at the Center of the Complaint

According to the NAACP of St. Louis, as reported by First Alert 4, the chapter has identified two airport projects designated as emergencies that it says bypassed open bidding altogether. The first is the Concourse D contract, which the chapter says was approved on Sept. 22 for more than $8.3 million and handed to Ben Hur Construction without the project ever being advertised or opened to public bidding.

The second project the NAACP points to is the remodeling of Lambert's operations center. Per the same account, that job was bid out in March 2021, but all three bids submitted were found noncompliant with Ordinance 70767, the city's rule governing minority- and women-owned business participation. Five weeks after that noncompliance was flagged, the project was redesignated an emergency and ultimately awarded to Ben Hur Construction, the chapter says.

What Ordinance 70767 Requires

Ordinance 70767 is designed to increase participation goals for minority-owned, women-owned, and city-resident businesses on city contracts, the report notes. The ordinance also carries teeth: it provides for a mandatory one-year disqualification penalty and liquidated damages for developers and contractors who fail to meet those participation goals, according to the chapter's account of the law.

A Pattern the Chapter Says Spans Years

The NAACP says this isn't an isolated incident. The chapter told reporters that seven airport emergency items have reached the Board of Public Service for votes over the past five years, and that four of those emergency projects were awarded in 2026 alone, totaling $17 million. The chapter also says Lambert's monthly emergency reports, a routine accountability measure, have not been issued since August 2022.

Separately, a Board of Public Service item reviewed by Citizen Portal shows the board heard a recommendation on Sept. 22 to approve up to $8,399,000 for renovation work at Lambert under Emergency Work Authorization No. 90000002-27, with board president Rich Bradley citing Ordinance No. 71876 as the authorization for the work.

Records Request and the Airport's Response

The NAACP is now pushing for the release of the airport's emergency findings, bids, and approvals, and it wants two audits that the chapter requested on Oct. 29 to be opened to the public. A Lambert Airport spokesperson said the airport received a Sunshine Law request from the NAACP for data tied to that morning's press conference and is currently working through it.

“We are currently responding to this request, so at this time, St. Louis Lambert International Airport has no comment,” the airport said in its statement. The airport's own public notices page, which lists signed Airport Commission minutes and meeting agendas dating into late 2026, directs anyone seeking a report or plan not already posted to submit a Sunshine Law and Public Records Request, a process the chapter is now testing directly.

Audits Already on the Books

City of St. Louis Comptroller records show Lambert has been the subject of multiple contract audits in recent years, though the evidence available does not detail their findings. One listing covers audit number 2022-APC08, with a report dated Aug. 10, 2023, examining the period from March 1, 2020 through April 30, 2021. Another, audit number 2023-APC03, carries a report date of July 17, 2023, and covers February 2017 through January 2021, while a third, audit number 2024-APC04, is dated Oct. 22, 2024. It is not established whether either of the two audits the NAACP wants opened corresponds to these listings.

For now, the central questions raised by the NAACP of St. Louis remain unanswered: what the two requested audits actually found, whether the emergency designations met the legal threshold required to skip competitive bidding, and what the released records will ultimately show. Lambert Airport has said only that it is working through the request.