Jim and Tracy Dunnier moved to Cape Coral from upstate New York in 2019 hoping to spend their retirement years quietly beside a backyard pool. Instead, they say they paid $60,000 toward a roughly $74,000 pool before the city halted construction, fined them $305, and left them paying another contractor roughly $70,000 just to finish what they had already paid for once.
The Dunniers are among several Southwest Florida homeowners who say they were left with unfinished pools, property liens, and unexpected expenses after hiring Naples-based Goliath CPS LLC, according to an investigation by WINK News. The company, owned by Terence Farrell, now faces more than $220,000 in civil court judgments across Lee and Collier counties, the station reported after reviewing court filings, state regulatory records, and homeowner contracts.
“This was our retirement,” Jim Dunnier said, describing a plan to live quietly by their pool after the couple, who have two grandchildren and have also lost two children, settled into life in Southwest Florida. After paying $60,000 across multiple installments toward the Goliath CPS quote, the Dunniers grew concerned over months of permitting delays, the station's report notes.
Cape Coral Halts Construction Over Permit Problems
Tracy Dunnier said Farrell altered another company's permit and put the Dunniers' names and address on it, after sending a Cape Coral pool permit application that listed the couple's property alongside credentials for Quality Pool Care of SWFL. Cape Coral Code Enforcement ultimately halted construction and fined the Dunniers $305 after finding the project lacked valid city permits and a licensed contractor, per the same account.
Farrell also provided the Dunniers a state contractor license number belonging to Eben Miller, who owns Cape Coral Pool Builders and is now working with Florida's Department of Business and Professional Regulation. Miller said Farrell used his license number without permission. The Dunniers said they ultimately spent about double their original pool budget, paying roughly $70,000 to another contractor to finish the job.
Naples Homeowner Paid More Than $100,000
Matt Simanski hired Farrell in June 2025 for work on his three-acre Naples property and paid Goliath CPS more than $100,000, the report states. Subcontractors later placed liens on Simanski's home after Farrell failed to pay them, and Simanski said he spent roughly $40,000 out of pocket to fix construction errors, replace missing equipment, and correct well-water staining.
A statutory demand notice dated March 2026 and reviewed by WINK's investigative team said two checks Goliath CPS wrote to Simanski in January 2026, totaling $19,200, were dishonored. Simanski said Farrell represented himself as a licensed contractor and that authorities knew he was unlicensed, the station's report notes.
A Third Homeowner's Pool Took Six Weeks to Finish — After Goliath CPS Left
In northeast Naples, Bob Colette hired Goliath CPS in 2024 after the company quoted him $105,000 for a pool. He waited eight months to secure a permit, and Farrell stopped communicating with him in June 2025. Colette said Farrell pocketed down payments intended for subcontractors, including $7,000 meant for a pool screen enclosure.
Colette eventually hired one of Goliath CPS's own unpaid subcontractors to finish the project, which took about six weeks once that subcontractor took over. By the time the pool was done, Colette said he had spent roughly $150,000 total — about $45,000 above his initial quote.
State Regulators and Courts Pile On Judgments
In May 2026, the Florida Department of Business and Professional Regulation issued a final order against Farrell following an administrative complaint, citing him for unlicensed contracting and imposing administrative fines and investigative costs, per WINK's reporting. Separately, courts across two counties have entered a string of default judgments against the company.
A Lee County circuit court entered a $172,500 default final judgment against Goliath CPS in December 2025 for unpaid excavation, backfilling, and material delivery work at the Casa Ybel Resort on Sanibel. Circuit Judge Michael T. McHugh granted a motion to show cause on October 6 after Goliath CPS failed to submit court-ordered financial disclosures, and ordered a writ of bodily attachment that would result in Farrell's incarceration if he did not comply within 10 days of being served. The owner of Tropical Maintenance of Southwest Florida told the station a warrant was out for Farrell's arrest because the court order was not followed.
In Collier County, a judge entered a $37,858.36 default final judgment — including treble damages — jointly and severally against Goliath CPS, Farrell, and Britney Marshall in February 2026 over two checks returned for insufficient funds. A separate Collier County judgment of $11,336.93 was entered in November 2025 against the same three parties for unpaid drywall and building supplies. Court records cited by the station also show Goliath CPS wrote two checks totaling $9,117.63 in July 2025 that were returned for insufficient funds, while SCP Distributors LLC sought a writ of garnishment against TD Bank in June 2026, and JPMorgan Chase Bank received a separate writ of garnishment in March 2026.
Subcontractor Chose Not to Lien Homeowners Already Struggling
Marshall was listed as president on Goliath CPS corporate credit applications but has since separated herself from the company, according to the report. Site development contractor Nevin McLaren, who hauled dirt and rock for Farrell's pools more than a year before the station's report, said he is owed more than $4,000 but chose not to place liens on homeowners' properties because he knew they were already in the same boat.
WINK's investigative team said it attempted to reach Farrell by email and phone, finding his primary business phone disconnected, and also called Marshall. Neither Farrell nor Marshall responded to the outreach, per the station's reporting.
What Florida Law Says About Liens and Unlicensed Contractors
Under Florida Statutes section 713.06, unpaid subcontractors or material suppliers who qualify under the law may generally enforce a payment claim against a property even if the owner already paid the contractor — though most lienors must serve notice on the owner before starting work or within 45 days of starting, and missing that deadline can serve as a complete defense against enforcing the lien. Separately, the 2026 edition of Chapter 713 of the Florida Statutes states that no lien exists in favor of a contractor, subcontractor, or sub-subcontractor who is unlicensed under the state's licensing statutes.
Unlicensed contracting complaints are not new to the region. A 2023 report from The News-Press noted that after Hurricane Ian, signs warning that contracting without a license was illegal appeared across Southwest Florida, around the same time the state's Department of Business and Professional Regulation charged three Southwest Florida men with unlicensed contracting.