Norwalk's Land Use and Building Management Committee voted unanimously to continue funding the Fire Station 4 project, whose price tag has climbed from $4 million to roughly $4.7 million. The 180 Westport Avenue firehouse, built in 1967, has never undergone major upgrades, and officials say the added cost comes after the city couldn't make its original budget work despite three rounds of bidding.
According to Norwalk Current, the city had set aside $4 million for the project but couldn't hit its estimated $3.8 million budget even after going out to bid three times to hire a construction manager. The updated numbers now include roughly $700,000 in additional trade costs and another $175,000 in so-called soft costs, pushing the total toward $4.7 million, per the Wisevoter report on the project. Project planners did manage to trim about $100,000 from the scope before the station's renovation plan was re-bid.
To move forward, the project would need a special capital appropriation of $773,591, along with sign-off from the City Council's Finance Committee and the full council. Whether that approval comes before the end of the year has not been determined. The committee's vote clears the way for the next steps, but the station's long-awaited makeover still has a few bureaucratic hurdles left.
What the Expansion Would Actually Add
The plan calls for a roughly 1,700-square-foot expansion that would let the department base another apparatus at the Westport Avenue building, the same report notes. Currently, the station houses four firefighters and a single vehicle. The renovation would also include new windows and an upgraded HVAC system, according to Nancy on Norwalk.
Under the plan, a ladder company would relocate from Station 1 at 90 New Canaan Avenue over to Station 4, while the rescue company would shift the other direction into Station 1, the same outlet reports. City officials have said that pest control, roof patches, and bathroom repairs have already addressed some of the building's reported maintenance issues, though those fixes stop short of the structural upgrades envisioned in the full renovation.
Rising Call Volume Behind the Push
Fire Chief McCabe presented call data to the committee showing Engine 4 ran 1,783 calls last year and had already logged 1,608 calls so far this year, with volume continuing to climb. The department has been dealing with substantial call volume.
That surge in demand is central to why officials are pushing to get another rig stationed at the Westport Avenue building rather than leaving it a single-apparatus house. Conte presented the updated project cost to the Fire Commission earlier this month as the numbers kept shifting upward.
A Construction Timeline Still in Flux
Construction could begin in February or March 2027 and take about nine months to complete.
Either way, the project remains funded through city spending, meaning Norwalk residents will bear the cost of the expanded firehouse. The Land Use and Building Management Committee, which oversees building projects across the city, had previously taken up other capital items in early November, including a referral of the Belden Library naming to a public hearing and a GMP amendment tied to Marvin Elementary's HVAC work, according to CitizenPortal.ai.
The Fire Station 4 project was ultimately awarded to a Norwalk general contracting firm after the earlier bidding attempts fell through. For now, the firehouse that has stood largely untouched since 1967 waits on one more round of council approvals before crews can break ground.