Oklahoma City/ Transportation & Infrastructure

OKC Drains Oklahoma River Basin for 632-Foot Bridge Ahead of 2028 Olympics

AI Assisted Icon
Published on November 24, 2026
OKC Drains Oklahoma River Basin for 632-Foot Bridge Ahead of 2028 OlympicsOKANA Resort — Site of Existing Pedestrian Bridge
Google Street View

The Oklahoma River basin between Walker Avenue and First Americans Boulevard is being drained, and it's not a drought problem — it's prep work for a brand-new pedestrian bridge planned at Lincoln Boulevard. The City of Oklahoma City confirmed the drawdown in a social media post Monday, framing it as the first visible step toward a project that will reshape how people move along the riverfront.

Why the Water Is Disappearing Downtown

According to the City of OKC

, the basin is being drained specifically to prepare for construction of the new crossing. As reported by

News 9

, the draining isn't just about clearing space for bridge piers — crews also plan to remove sediment buildup that has accumulated in the basin and complete upgrades to a sewer main while the water is out of the way. It's the kind of multitasking that makes sense when you're already draining a stretch of river for months.

That downtime comes with a real cost for recreational users. The same News 9 report notes that rowing activities in the Boathouse District are temporarily unavailable while the basin sits empty, a disruption for a stretch of river that's become synonymous with competitive and recreational rowing in Oklahoma City. The station reports the city expects to refill the basin in spring 2027, giving rowers a return window, though an exact resumption date for the sport itself hasn't been specified.

What the New Bridge Will Actually Look Like

Per News 9, the planned pedestrian bridge will connect the north and south Rivershore Trails and measure 30 feet wide. The design calls for decorative handrails, illuminated pedestrian pathways, and a large architectural arch meant to serve as a visual landmark along the river. The span is set to rise just east of the Lincoln Boulevard bridge, according to a separate report from Yahoo.

That arch and the bridge's other aesthetic flourishes didn't come cheap, and the Oklahoma City Council had to sign off on the extra spending separately. The council voted unanimously on Oct. 13 to use up to $4 million from voter-approved general obligation limited tax bonds specifically for the arch and other decorative features, Yahoo reported.

The Bridge's Price Tag

Yahoo, republishing the Oklahoman's original reporting, reports a $23 million project total, with the remainder funded by ODOT through a federal grant.

Construction on the bridge is set to start later in 2026, Yahoo reports. Yahoo reports the bridge should be completed by May 2028 — just ahead of the Olympics — though officials could not guarantee the architectural arch would be finished in that same window.

Part of a Bigger Riverfront Push

The Lincoln Boulevard span isn't happening in isolation. KFOR reports that ODOT plans to replace the Interstate 35 bridges over the Oklahoma River in the coming years, part of a broader wave of river crossing upgrades moving through the city. Oklahoma City has also already delivered on part of that vision: the first of three planned pedestrian bridges across the river opened at the OKANA resort in September 2025, which The Oklahoman described at the time as the first-ever pedestrian bridge over the river.

For now, the stretch of river between Walker Avenue and First Americans Boulevard is being drained to prepare for the bridge. Rowers and riverfront regulars will have to wait for the expected spring 2027 refill to see the basin back to its usual self.