Plainfield BOE Weighs $23M Fix or Demolition for Shuttered BUF I School

AI Assisted Icon
Published on November 22, 2026
Plainfield BOE Weighs $23M Fix or Demolition for Shuttered BUF I SchoolCentral Ave. & W. Seventh St. — Approximate Site of BUF I Building
Google Street View

Construction has come to a standstill at Plainfield's BUF I building, a nearly century-old structure at the intersection of Central Avenue and West Seventh Street, as the Board of Education waits on updated repair estimates before deciding whether to renovate or demolish it. The district says funding has already been set aside to bring the building back into use, but that money remains on hold until new numbers come in.

Why Work Stopped

According to a Frequently Asked Questions document posted by Plainfield Public Schools, “All construction at BUF I has been halted pending updated repair estimates.” The same document states that the Board has requested additional information from vendors before moving forward. The district also confirms that funding has been allocated to bring BUF I online, but that those updated repair estimates are still pending.

The pause comes as the Board prepares to lay out its options publicly. Per TAPinto, the Plainfield Board of Education will present options for BUF I's future at its December business meeting, with a final decision expected early next year.

A Building With a Complicated History

BUF I was constructed in 1929, and the district purchased the property for $5.2 million in June 2025, the outlet's reporting notes. Because the school district could not conduct structural testing before taking ownership, problems surfaced only after the purchase closed. A structural engineer found severe structural conditions requiring emergency work in September 2025, and that same engineer recommended repairs the following month, when the district also agreed that major systems including electrical wiring needed upgrades.

DMR Architects, which provides architectural services for the Board, had been involved with the site well before those findings. The firm assessed the property's condition in November 2024, began site visits with engineers and district staff in May 2025, and issued an order-of-magnitude renovation budget by March of that year. At one point the district notified DMR of a renovation budget of $4 million, and the firm went on to complete construction documents in January 2026.

Three Options, Wildly Different Price Tags

By March 2026, DMR Architects was asked to compare limited and extensive renovation costs, and the firm ultimately outlined three renovation options for BUF I. Minimal renovations could make the building safe for daily use at a cost of approximately $6 million to $7 million, the outlet's reporting states. Limited renovations were estimated at around $6 million, while extensive renovations could run as high as $23 million depending on scope and the timing of the estimate — up from an earlier DMR estimate of roughly $14.8 million for the same extensive scope. By comparison, demolishing BUF I was estimated in June 2026 to cost $2.5 million. The district's renovation budget has been described as around $5 million, well short of the costlier options on the table. One renovation plan included moving administrative offices into the building's former childcare center and closing its classrooms, the same reporting notes.

Board Members Press for Answers

The cost debate has not gone unchallenged inside Board meetings. Laura Miranda-Browne asked directly about the cost of demolishing BUF I and criticized a lack of financial detail in the June meeting minutes, according to the outlet. Fernando Robledo, AIA, who led the June presentation, declined to recommend either demolition or renovation, citing multiple factors, per the same reporting.

Confusion has lingered even among board members themselves. Hanae Wyatt said board members had not received all of the information shared at the June presentation, and at the November business meeting, Wyatt stated that no demolition decision had been made. A June 2026 report had similarly indicated that no final decision had been made regarding BUF I's future, with the Board continuing to review available options before determining a path forward, though that earlier account carries lower confidence than the district's own more recent statements.

The Stakes of Waiting

Officials have acknowledged that time is not necessarily on the district's side. Aging building systems at BUF I would need eventual replacement regardless of which path the Board chooses, and the structure may require substantial additional expenses over the next decade. Renovations to older buildings can also reveal previously unknown problems that increase construction costs beyond initial estimates, a risk that looms over any renovation plan the district ultimately pursues.

For now, the district points to a success story next door as proof that major overhauls can pay off: BUF II, now known as Plainfield Early Learning Center, is operational, according to the district's FAQ document. Whether BUF I follows a similar path, or meets the wrecking ball instead, should become clearer when the Board presents its options in December and makes a final call early next year.