Renovating Baltimore Polytechnic Institute and Western High School's shared campus still requires $110.7 million in funding. A substantial gap remains as construction planning moves forward.
The funding need was reported by the Baltimore Sun, which cited a $110.7 million gap for the project. The renovation covers roughly 681,200 gross square feet across the campus the two schools share, according to project bid documents posted by the Maryland Stadium Authority. That scope includes replacing major mechanical, electrical and plumbing systems along with interior finishes and storefront assemblies, the same documents show.
What the Renovation Actually Involves
Rather than a ground-up rebuild, the project is largely an interior overhaul. An April 2025 construction-management request for qualifications described a complete renovation of the existing facility, with the possibility of a small addition to address ADA concerns. That same document pegged the building's specified area at 681,095 square feet, with capacity for 3,430 students — a figure close to, but not identical to, the 681,200-square-foot estimate cited elsewhere in the project's bid documents, without explanation for the discrepancy.
Bid documents anticipated construction beginning in summer 2026 and wrapping up in summer 2030, with each school's renovation phase expected to take about two years. Those dates reflect the anticipated schedule laid out in planning documents rather than confirmation that work has started.
Funding Already Shifted to Cover Construction Costs
Some money has already been redirected to the project. The Interagency Commission on School Construction approved shifting $6.882 million in fiscal year 2024 design funding for Baltimore Polytechnic Institute's renovation into fiscal year 2026 construction funding, drawing from Baltimore City Public Schools' reserve account, according to commission meeting minutes from June 2025. The commission approved a similar move for Western High, shifting $5.078 million in design funding into construction funding from the same reserve account.
Those same minutes note that the Poly and Western projects had also received funding under the Built to Learn program at an earlier March 2025 commission meeting. The Maryland Stadium Authority's board agenda for its November 4 meeting listed a second guaranteed maximum price item for the Poly-Western project under its Built to Learn contracts.
School Construction Funding Statewide
Maryland's Capital Improvement Program for public school construction has averaged at least $280 million annually in recent years, per the commission.
Part of a Larger Push to Rebuild Baltimore Schools
Poly-Western is one piece of a much bigger citywide effort. More than $400 million was planned for renovations at five Baltimore City schools — City College, Polytechnic Institute, Western High School, Frederick Douglass High School and Joseph C. Briscoe Academy — according to WBAL-TV. That report also credited the Baltimore 21st Century Schools program with playing a leading role in building or renovating 28 city schools so far.
Two of those five schools have already seen their renovations completed. Frederick Douglass High School and Joseph C. Briscoe Academy received a combined $118 million renovation that brought both schools together under one roof, with construction beginning in 2024 and wrapping up, WBAL-TV reported separately. WMAR-2 News has reported that students at schools included in the broader renovation plan move to swing-space locations at other schools while the work is underway.