Port Washington Broke Records Law Hiding Data Center Emails, Judge Rules

AI Assisted Icon
Published on November 25, 2026
Port Washington Broke Records Law Hiding Data Center Emails, Judge Rules100 W Grand Ave — Site of Data Center Records Dispute
Google Street View

An Ozaukee County judge has ruled that the city of Port Washington broke Wisconsin's open records law while fielding a request for documents tied to its massive data-center project, finding that officials dragged their feet for months and intentionally left out key email attachments. Judge Adam Gerol ordered the city to pay a $100 fine and $1,000 in punitive damages to Lynde Uihlein, the woman who filed the request, with a separate hearing set for January 2027 to sort out her attorney's fees.

A Records Request That Took Months to Answer

Uihlein asked the city in August 2025 for records about the data center, including communications and draft agreements involving city officials and project representatives. According to FOX6 News Milwaukee, Port Washington did not respond to her request until nearly four months later — and only after she sued. The city eventually turned over emails, though attachments arrived months after the initial batch, along with text messages pulled from city officials' personal cell phones.

As reported by Ozaukee Press, Uihlein made her formal request on Aug. 5, 2025, seeking communications between city officials and representatives from Vantage and Kapur Engineering. She did not receive any response until after filing her lawsuit that November, the paper reported. Gerol determined that the city's failure to hand over complete email attachments as part of its response was intentional, not accidental.

Judge Says City Worked Harder to Withhold Than to Comply

Gerol did not mince words in his assessment of the city's handling of the request. He said there appeared to be a greater effort to withhold information than to actually respond to it, and he called the city's overall efforts on the request entirely insufficient. The judge ordered Port Washington to conduct a thorough search — including the city clerk's own records — and turn over any documents it had not already produced.

Christa Westerberg said the public was entitled to know these facts before the community was changed by the data-center project. Port Washington's city attorney acknowledged shortcomings in the response but said the city ultimately took substantial steps to fulfill it. Per the Ozaukee Press report, the attorney said the city recognizes its initial response to Uihlein's Aug. 5 request fell short of what should have occurred, and city attorneys separately said that initial response was not timely.

City Cites Cost and Volume of Records

City attorney Mark Schmidt said the request required Port Washington to produce more than 5,400 pages of emails, text messages and other documents, and that searching, identifying and producing those records was a substantial cost to the city. Port Washington did not charge Uihlein a fee for producing the records. City attorneys also noted that her request was part of a broader increase in records requests centered on the data-center project.

The $15 Billion Project Behind the Dispute

The records fight centers on a sprawling data-center campus that Vantage, Oracle and OpenAI are teaming up on, a project reported to be worth roughly $15 billion. The companies now plan to invest more than $15 billion in the Port Washington campus, which will include four data-center buildings, according to Wisconsin Public Radio. Separately, BizTimes reported that Port Washington's Common Council approved an $8 billion data-center campus in August 2025, a figure that differs from the $15 billion sum cited elsewhere; it is not clear from available reporting whether the two numbers refer to different phases or scopes of the same project. Engineering News-Record has reported that the development is expected to dwarf Microsoft's $3.3 billion, 315-acre data-center campus under construction in Mount Pleasant, Wisconsin.

Part of a Wider Pattern of Secrecy Around Data Centers

Port Washington's records dispute comes amid broader scrutiny of how Wisconsin communities have handled data-center negotiations. Wisconsin Public Radio reported that nondisclosure agreements have surfaced in at least five Wisconsin communities with proposed or developing data-center projects, including the town of Beloit. That town signed an NDA with Cambrin LLC in February 2025, more than a year before publicly announcing preliminary discussions about a possible data center there.

For now, Port Washington faces the task of completing a fuller records search under Gerol's order, while the question of how much the city will owe in attorney's fees remains unresolved until the January 2027 hearing.