Scottsdale has no rules on the books for data centers, and city officials say the kind of massive, power-hungry facilities popping up elsewhere in the region probably aren't coming here anyway. But the City Council isn't waiting to find out. Members have directed the city attorney to start exploring regulations for large-scale data centers before any application ever lands on a desk.
The directive, detailed by ABC15 Arizona, comes as Scottsdale's current city ordinances do not specifically define or regulate data centers at all. No timeline has been set for when the council will actually take up the issue, but the move puts Scottsdale among a growing list of Arizona cities and counties trying to get ahead of an industry that has expanded rapidly to power cloud computing and artificial intelligence.
Scottsdale isn't starting from zero. The city already has two smaller data centers near Scottsdale Airport that have operated since around 2000, and city staff say they have never caused problems, functioning much like a large office or warehouse. That track record hasn't stopped officials from wanting more structure in place should something bigger come calling.
Why Scottsdale Probably Won't Land a Hyperscale Facility
Part of the calculus is simple geography. Scottsdale officials said the city is unlikely to attract massive data-center facilities because it doesn't have the land other communities do. As one official put it in comments reported by ABC15 Arizona, “We simply don't have the site availability that some of the other communities across the region have.”
That scale gap matters because of just how big these projects have gotten. Existing community data-center projects run between five and 15 megawatts, while the smallest incoming hyperscale facilities now start at 200 megawatts, according to the same ABC15 Arizona report — a jump that underscores why land-constrained cities like Scottsdale are largely being passed over by the industry's biggest players.
Council Members Split on Urgency, But Agree to Act
Not everyone on the dais saw the need for the exercise. Councilman Adam Kwasman argued that data centers aren't currently an issue in Scottsdale and that continuing the discussion amounted to grandstanding, per ABC15 Arizona's reporting. He ultimately supported the motion anyway, giving the city attorney the green light to explore regulations despite his objection.
Mayor Lisa Borowsky took a more cautious stance, saying the city needs to be prepared if an application does come in. Councilwoman Solange Whitehead went further, laying out specific worries that could shape any future ordinance: noise, water usage and energy demands. Those three concerns echo what's playing out in several other Arizona communities already grappling with data centers in their backyards.
Other Arizona Cities Are Already Writing the Rulebook
Scottsdale's cautious first step arrives as data centers have become a flashpoint for communities across Arizona, with several cities and counties moving well beyond the exploratory stage. According to KJZZ, Pima County has temporarily banned data centers while leaders consult with industry experts and local development staff, and a proposed county ordinance would require a Type III conditional use permit while prohibiting open-loop cooling systems.
Marana amended its data-center zoning code on Oct. 20 to address low-frequency noise from mechanical equipment, with stronger penalties for violations, the station reported. Chandler went through a similar reckoning years earlier, creating a specific noise ordinance and zoning code in 2022 after residents complained about persistent, disruptive noise from a CyrusOne facility. Gilbert, meanwhile, postponed a vote on its own proposed data-center zoning ordinance until December to allow more discussion with industry and planning consultants.
Maricopa is weighing some of the most detailed rules yet. Proposed regulations there would require standalone data centers to secure both a planned area development approval and a conditional use permit from the city council, according to InMaricopa.com. The draft rules would also force data-center buildings to sit at least 500 feet from residential zones, schools, parks, hospitals and day cares.
Water and Power Concerns Loom Large Statewide
Water usage, one of Whitehead's three flagged concerns, has drawn particular scrutiny from researchers. The on-site cooling process at data centers itself uses a relatively modest amount of water, according to Wyoming Public Media, but the electricity these facilities demand can drive up water use at power plants far beyond the data center site itself. A Ceres study cited by the outlet estimated that water use tied to data-center electricity needs could rise by as much as 400% if all currently planned facilities get built, reaching 14.5 billion gallons a year statewide. At least nine Arizona water utilities had already adopted rules similar to Phoenix's large-water-user ordinance as of 2025, per the same report.
Opposition on the ground has followed similar lines. Public comments against a proposed data-center campus in Casa Grande cited concerns about water and power use, rising utility rates, community impact and sheer project scale, according to AZBEX. The Casa Grande Planning and Zoning Commission nonetheless approved a conditional use permit on Oct. 1 for a 954-acre data-center campus south of Montgomery Road and Maricopa-Casa Grande Highway — one of three large-scale projects planned around the Phoenix region, alongside facilities in Buckeye and Eloy, according to Data Center Dynamics.
Phoenix's own experience shows regulation can bring unintended complications. After the city adopted data-center rules in 2025, some landowners sought compensation, and the city ended up issuing waivers that gave four claimants permission to build anyway, according to Tucson.com. It's a cautionary data point for Scottsdale as its own attorney begins sketching out what local rules might look like.