A King County Council committee voted unanimously to approve the planned alignment and stop locations for RapidRide R, the long-awaited replacement for Metro's busy Route 7 between Rainier Beach and downtown Seattle. The project, expected to cost $91.2 million and open by 2032, will consolidate stops along Rainier Avenue while eliminating the existing South Prentice Street loop south of South Henderson Street.
A Transit Line Years in the Making
RapidRide R has had a long and bumpy road to this point. As reported by The Urbanist, initial groundwork for the corridor began in 2019 and was halted shortly afterward due to the pandemic and funding delays. Route 7 is Metro's second-busiest route and runs along what the Seattle Times has described as one of the city's busiest arterials, shared with the Route 9. At one stop near Rainier Beach High School, the Times found ridership had climbed to 120% of its 2019 level. The Times also reported that stop 8110 retained 95% of its 2019 ridership in 2020.
When the line opens, per Seattle Transit Blog, it will travel between Rainier Beach Station and downtown Seattle on Rainier Avenue, including a deviation to the station itself. The outlet reports that Tuesday's committee vote establishes the route's path and general station locations, while additional project components such as transit priority infrastructure, new crossings, and sidewalk improvements will be finalized in later project stages.
Stop Cuts Draw Pushback, Some Restored
Earlier versions of the plan drew sharp criticism from Rainier Valley residents, transit advocates, and disability advocates over the scale of proposed stop eliminations, the same outlet's reporting notes. A prior proposal reviewed by the South Seattle Emerald would have eliminated up to 36 stops — 16 north of South Henderson Street and 20 south of it — while an earlier Urbanist report pegged the original concept as consolidating 67 stops along the corridor into 45 when counting both directions.
Metro has since walked back some of those cuts. Two stops near Mount Baker that were slated for possible elimination will now be retained following community feedback, and the updated plan restores stops on Rainier Avenue at Bayview Street and at State Street and Grand Street, per the same Seattle Transit Blog report. Some potentially eliminated stops are served by other bus routes. Still, the agency plans to eliminate high-use stops including South Cloverdale Street and South Charles Street. The plan also eliminates the South Prentice Street loop, while Metro considers changes to maintain connections south of Henderson Street.
Councilmember Addresses RapidRide Service
Councilmember Rhonda Lewis, the ordinance's sponsor, addressed RapidRide service.
Metro restored two stops in response to feedback.
The current plans also omit transit priority treatments along South Jackson Street through the International District.
Funding Fight and What's Still Undecided
County Executive Girmay Zahilay, who has made the RapidRide R overhaul a priority, proposed moving up funding for the project, according to The Urbanist.
Metro says it's still evaluating connections for riders south of Henderson Street, with potential changes under consideration for Routes 106, 107, and 9, and the agency is separately planning a southeast Seattle route restructure for 2028 or 2029 that could adjust other routes to help back-fill coverage lost when the Prentice Street loop goes away. The RapidRide R ordinance requires the county council to be notified of any future changes to the stop plan. City of Seattle crews have already added bus lanes along Rainier Avenue in recent years, and the finished project is expected to include stop infrastructure upgrades and speed and reliability improvements.
Rebecca Saldaña is set to take office as the District 2 councilmember next week, and the full King County Council is scheduled to vote on the ordinance next week as well.