Spring Lake Township has officially opened a new non-motorized pathway along Hickory Street, giving neighbors who once walked and biked alongside passing cars a dedicated route of their own. The 0.7-mile, 8-foot-wide path runs along the south side of Hickory Street between Fruitport Road and 148th Avenue, connecting residents to other trails in the area.
Neighbors and community leaders gathered Tuesday for a ribbon-cutting ceremony at the entrance to Hickory Woods, according to the Grand Haven Tribune. Dale and Barb Swihart biked to the event, and Barb described the new trail as fun to ride on.
Residents along the corridor had walked and biked alongside passing traffic before the path opened. The new path gives them a dedicated route of their own.
Project Features
The project includes pedestrian crossings at both Fruitport Road and 148th Avenue.
The pathway was funded by the township's millage for new bike paths, which voters approved in 2024. That vote, held in August 2024, passed by a margin of 2,950 to 1,815, according to MLive, approving 0.50 mills for ten years, from 2024 through 2033.
Part of a Bigger Push for Trails
Spring Lake Township's non-motorized path page lists more than 25 miles of existing pathways across the community, a network supported by separate voter-approved millages for new construction and ongoing maintenance, per Spring Lake Township. The township's page had listed Hickory Street, from 148th Avenue to Fruitport Road, among projects under way or upcoming for summer and fall of this year.
An earlier estimate put the start of Hickory Street path construction in spring or summer 2026. An earlier Grand Haven Tribune update reported a four-week contractor delay and said work on the Hickory Street path was beginning that week.
The Hickory Street pathway was part of the township's trail work, alongside a Rannes Street path.
Fitting Into a Regional Trail Expansion
The Hickory Street opening is part of a broader, phased expansion of trails across the township. A 2025 report from Ottawa News Network said phase two of that expansion was slated to begin in spring 2026 and would encompass Hickory Street from 148th Avenue to Fruitport Road. Elsewhere in the region, the outlet noted, the completed Bayou Segment of the Idema Explorers Trail stretches six miles and links more than 1,000 acres of parkland, while the Grand Crossings Loop runs 24 miles and fully encircles the Grand River.
The broader trail expansion is funded by two 10-year millages approved by voters on Aug. 6, 2024, and Spring Lake Township has more than 25 miles of trails overall.