Residents in St. Charles County are raising pointed questions about Ameren Missouri's plan to build a massive new natural gas plant next to its existing Sioux coal facility in West Alton, with worries ranging from water use to who ultimately foots the bill. The utility presented its proposal at a public meeting in the county, and the reaction has been anything but quiet.
Ameren Missouri is seeking approval for a 2,100-megawatt combined-cycle natural gas plant, according to a filing with the Missouri Public Service Commission. The utility says it designed the facility to provide dependable, round-the-clock baseload energy, and per Ameren staff, the plant could begin supplying power to Missourians by 2031 if regulators sign off. As reported by KSDK, the proposal has sparked concern among both residents and officials about whether it's actually necessary.
At the heart of the debate is money — and how much of it customers might be asked to put up before the plant even generates a watt of power. Ameren is seeking to use a financing method called Construction Work in Progress, which would let the company start collecting funds from customers while the West Alton facility is still under construction. The Missouri Legislature enacted the law allowing this kind of arrangement in 2025, and Ameren hopes to apply it to one of its first major projects under the new rules.
Who Pays, and How Much?
The potential price tag for the West Alton energy center is redacted in Ameren's state filings, according to STLPR. That hasn't stopped the company from touting potential upside: Ameren has said customers could see $21 million in projected base-rate savings over the next two years, a figure the utility ties to new data-center customers that have signed on. The station also reported that customers have signed agreements to buy 2.8 gigawatts of power load from Ameren, much of it tied to large-load customers including data centers.
John Clizer said large-load customers, primarily data centers, are driving the need for the plant, and he argued those customers should pay the full cost of their energy. Ameren has said it agrees that large-load customers should pay their share. But Clizer pushed back on one of the utility's central arguments, saying Construction Work in Progress does not automatically lower customer costs — a direct challenge to Ameren's claim that the financing method could reduce ratepayer expenses. Rob Dixon, per Ameren, said the plant is needed to provide reliable, round-the-clock baseload energy, while the Missouri Office of the Public Counsel disagrees that the state needs the proposed plant at all.
Under Missouri law, the stakes of that disagreement are significant. The statute governing Construction Work in Progress specifies that an electrical corporation “shall not be eligible” for the financing on resource additions the commission has not approved, according to the Missouri Revisor of Statutes. The same statute text says the commission must determine the allowable amount in a separate rate proceeding. The Missouri Public Service Commission must weigh multiple factors before deciding whether to grant that funding mechanism for the West Alton project.
Water Use and Neighborhood Worries
For some residents, the concerns are less about spreadsheets and more about what's happening in their backyards. Andy Young said he's worried about water use and contamination tied to Ameren's projects in the area, noting that two gas peaker plants and a solar farm are already planned nearby. Young said one of those peaker plants alone uses huge amounts of water in a single hour, a detail that has fueled broader unease among residents about the cumulative effect of so much new energy infrastructure clustered in one corner of St. Charles County.
Ameren has said the West Alton plant would operate concurrently with the Sioux Energy Center if approved. Ameren hopes to start construction in mid-2027, according to KSDK's reporting on the utility's timeline.
A Bigger Pattern Across Ameren's Territory
The West Alton proposal doesn't exist in isolation. Ameren Missouri's broader 20-year planning document, filed with regulators, lists nine natural gas plants for construction over the next two decades — up from just two in its 2023 plan, STLPR reported in a separate story on the utility's long-range outlook. That same plan projects natural gas will grow from roughly 5% of Ameren's current resource mix to 60% by 2045, even as the company zeroes out coal entirely, according to Utility Dive.
Ameren's preferred resource plan assumes total load growth of 2.9 gigawatts by 2030 and 5 gigawatts by 2035, per slides the company filed with its Integrated Resource Plan. Notably, the 2026 plan also dropped language about a net-zero emissions goal that had appeared in Ameren's 2020 and 2023 planning documents, the station's report on the filing noted. Separately, rising construction costs for plants like the one proposed in West Alton are being driven in part by a parts shortage tied to the broader data-center boom, per the same STLPR account.
The West Alton case also isn't the first time Missouri regulators have confronted this kind of financing request. The state recently allowed Liberty, a smaller electric utility in southwestern Missouri, to use Construction Work in Progress for its own natural gas plant — a precedent Ameren's request will likely be measured against. Residents near West Alton, meanwhile, remain focused on more immediate concerns: how the proposed facility will affect the people who live closest to it, long before the first shovel goes into the ground.