Texas Beach Bridge Reopens in Richmond After Four-Year Closure, But Watch for Surprise Shutdowns

AI Assisted Icon
Published on November 20, 2026
Texas Beach Bridge Reopens in Richmond After Four-Year Closure, But Watch for Surprise ShutdownsSource: Eli Christman / Wikimedia Commons

The Texas Beach Bridge, the only land route into one of Richmond's most beloved stretches of the James River, is open to the public again after being closed since September 2022. The reopening ends a yearslong wait for hikers, swimmers and river regulars who had been cut off from a mile-long stretch of beaches, rocks and trails tucked along the water below the Fan neighborhood.

According to The Richmonder, the bridge closed in September 2022 after officials discovered severe structural damage during an inspection. As Richmond Times-Dispatch reporter Zach Joachim detailed, engineering firm Timmons Group found the span structurally unsafe for public use, per the city, after that September 2022 inspection.

The bridge's closure lasted more than four years, the Richmond Times-Dispatch reported. Some persistent rivergoers found their way in anyway, illegally crossing the railroad tracks or hiking in via trails from Pump House Park, according to the same report.

A Crossing Complicated by Active Rail Lines

Part of what made repairs so slow was the bridge's location: it crosses active CSX railroad lines, and the work had to be carefully timed to avoid impacting rail traffic, sometimes requiring special flaggers, the Richmonder reported. That logistical tangle helped push the timeline well past the city's early hopes.

City officials initially hoped to reopen the bridge by summer 2024, according to Axios Richmond, but that target slipped. By August 2024, with the original completion date nowhere in sight, WRIC ABC 8News reported the project still wasn't nearing completion. Construction work didn't actually begin until 2025, Axios Richmond reported. By March 2026, Axios Richmond reported the project was on schedule to wrap up by December, the deadline tied to its federal funding.

What Got Fixed, and What It Cost

Repairs included replacing the old concrete walkway with a metal walkway and significant construction on the stairway descending from the bridge's south end to the trails, according to the Richmond Times-Dispatch.

The $2 million project was funded entirely through city grants received under the American Rescue Plan Act, the Richmonder reported.

More Closures Could Still Be Coming

Even with the bridge walkable again, the city's parks department says the work is substantially completed but final touches will still require closures, according to the Richmonder. Officials have said the pedestrian bridge may need to close again, and that closure could happen without notice, the outlet reported.

The city will schedule an official ribbon cutting once all work is complete, the Richmonder reported.