Pender County Schools has pulled the Topsail Middle School renovation back from the brink of a budget blowout, landing on a revised $30.98 million plan that squeaks in just under the Pender County Board of Education's $31 million cap. The board voted unanimously Tuesday to approve that cap and move forward with the trimmed-down scope, after cost estimates had ballooned far past the project's original price tag.
The project started with an initial budget of $30 million, according to Port City Daily, but updated construction estimates later soared to 69.7% above that figure — more than $20 million over the original number, the outlet reported in late October. By September, preliminary budgeting had the project at $30 million while construction cost estimates had already reached $45.97 million, per the same publication's earlier reporting. An even larger figure had circulated before that: WWAY reported the full renovation was once estimated to cost approximately $50 million.
Trimming the Scope to Close the Gap
To close that gap, district staff cut the renovation scope by $19.2 million. Removing planned classroom renovations in Building 1 saved around $4.6 million, while swapping the gym HVAC setup to standalone units instead of a central chiller system, and scrapping training room doors and rebuilt restrooms, trimmed costs further. Buildings 3 and 4 gyms still get new HVAC systems, roofing, wall panels and windows under the revised plan.
Site work took a hit too: new asphalt, curb and gutter were removed from the plan, and the number of sidewalks was reduced, saving approximately $3.9 million combined. Two planned building connectors were dropped altogether. Construction changes also helped — swapping concrete block for metal studs on the exterior walls of Buildings 1 and 5 cut $1.7 million, even as those same buildings will now use brick instead of metal panels on the outside.
Tennis Courts and Greenhouse Cut From the Plan
Some of the more ambitious additions didn't survive the budget squeeze. The renovation plan eliminated new tennis courts and a new greenhouse entirely, according to WECT, which also reported that Buildings 1 and 5 remain the primary renovation areas while planned work on Buildings 2, 3 and 4 has been scaled back. One addition did survive, though: around 110 paved parking spaces near the current entrance are still part of the plan, WECT reported.
The revised numbers now put the project's predicted cost below the $31 million budget by just $21,992 — a margin board member Don Hall acknowledged was uncomfortably thin. “I don't really like it being so close, but we need to proceed,” Hall said, according to Port City Daily's reporting.
Board Also Eyes Portable Classrooms for Reuse
Beyond the cost cap, the Pender County Board of Education also voted unanimously Tuesday to authorize staff to evaluate the portable classroom units on the Topsail Middle campus for possible reuse elsewhere in the district, according to WWAY. The outlet reported that the board's vote to cap the project at $31 million and move forward with the revised scope was also unanimous.
The push to renovate Topsail Middle comes as enrollment pressure mounts. Superintendent Brad Breedlove has said the school already serves more than 2,000 students, with enrollment projected to top 3,000 within the next decade, WWAY reported during an earlier tour of the campus amid the budget concerns. For now, the district's focus is on keeping the scaled-back renovation inside its newly capped budget as work moves ahead.