Tracy's City Council voted unanimously on Nov. 17 to pump another $5.65 million into the construction and engineering contracts for the I-580/Patterson Pass interchange, a project that's already about 70% finished and carries a budget that's now crept close to $67.5 million. The increase covers a $4 million bump to the contingency fund tied to the main construction contract and a $1.65 million bump to the firm overseeing construction management.
Where the Extra Millions Are Headed
According to ttownmedia.com, the council's action lifted the construction contract's contingency fund from nearly $6.4 million to nearly $10.4 million. That contract belongs to Berkeley-based O.C. Jones & Sons, which was originally approved in June 2024 at nearly $42.6 million. Separately, the construction management contract held by Manteca-based Dewberry Engineers Inc. climbed by $1.65 million, bringing it to just over $6 million after starting out valued at nearly $4.3 million and getting a smaller $81,634 bump in 2025.
City Engineer Even Marcelo said the final project cost will still depend on further changes as work continues, per the same report. Cost increases so far have stemmed from unexpected field conditions, extensive utility coordination, and design refinement, the outlet notes.
A Project Years in the Making
The interchange itself — a new diverging diamond design at Interstate 580 and Patterson Pass Road/International Parkway — has been in the works for years. The city first locked in funding in 2020, when it landed a $24.9 million grant from the California Transportation Commission's Trade Corridor Enhancement Program, as reported by ttownmedia.com. When the council awarded the original construction contract, O.C. Jones & Sons came in as the low bidder among four companies, with bids running as high as nearly $50.7 million, the outlet reported at the time.
The project's roughly $67.5 million budget now draws from a patchwork of sources. The Tracy Infrastructure Master Plan Fund, which is funded through developer impact fees, contributes about $25 million, while the Trade Corridor Enhancement Program grant adds $24.9 million. The rest comes from Measure K, gas taxes and regional traffic impact fees. Earlier coverage from ttownmedia.com had also detailed separate funding breakdowns of $14 million in developer fees, $8 million in regional transportation impact fees and $2.5 million in county Measure K revenue tied to the project's earlier stages.
Council Moves From October Carried the Project Forward
On Oct. 20, the council approved transferring $4.6 million from general fund reserves into the infrastructure master plan fund and accepted $950,000 in federal Transportation Improvement Program funding for the project, bringing the city's total committed funding to about $61 million as of October. That followed an Oct. 12 recommendation from the Tracy Finance Committee, which, according to citizenportal.ai, called for a $5,563,946 appropriation along with a $4,613,946 interfund loan and the acceptance of $950,000 in repurposed FTIP funds. That same committee report said staff estimated the project was 60% complete at the time.
A separate project update from citizenportal.ai described the interchange as about 70% of the way through its construction schedule, with Miguel Hernandez, the City of Tracy's construction project manager, noted in that account. That update also said traffic was expected to shift to a new ramp layout in late October, though the timing could change due to weather.
What Drivers Can Expect
Once finished, the interchange will feature three northbound lanes heading into the industrial area, two lanes heading toward Patterson Pass Road, bike lanes running in each direction, and a bicycle and pedestrian path down the middle, according to ttownmedia.com's earlier reporting. The new interchange is expected to open in spring 2027, though Marcelo's comments leave open the possibility that both the schedule and the final price tag could still shift before construction wraps.