Warm Springs Tribes Lock In Massive Solar Project to Power Up PGE Grid

AI Assisted Icon
Published on November 20, 2026
Warm Springs Tribes Lock In Massive Solar Project to Power Up PGE GridSource: Jacob coffin / Wikimedia Commons

The Confederated Tribes of Warm Springs have finalized a lease agreement for a major utility-scale solar power and battery energy storage project that will supply power to Portland General Electric, marking a significant new chapter in the tribes' energy ambitions. The project, named Salmonfly, is being developed by Warm Springs Power & Water Enterprises in partnership with developer BrightNight.

Warm Springs Power & Water Enterprises finalized the Salmonfly lease agreements with BrightNight on November 12, according to Cascade Business News. Tribal Council approved the underlying lease back in October, setting the stage for this month's finalized agreements. Portland General Electric will serve as a utility partner on the project, according to The Bulletin, with the utility needing more renewable energy and storage flexibility to meet rising demand and state decarbonization mandates, as The Business Journals reports.

Where the Project Will Sit and How Big It Could Get

Sources differ on exactly how much reservation land Salmonfly will occupy. The Bulletin's more recent reporting describes the project as planned for approximately 1,500 acres of southern Warm Springs reservation land, while a project assessment filed for public comment describes a footprint of roughly 2,000 acres. That same assessment outlines plans to develop up to 250 megawatts each of solar generation and battery storage, whereas a separate report on Portland General Electric's build-transfer agreements, carried by Metal.com, lists Salmonfly at 199 megawatts each of solar and storage.

Whatever the final numbers turn out to be, the project is planned to connect at the Round Butte Substation, tapping into transmission infrastructure already owned by the Tribes, per the same Bulletin report. The project assessment goes further, describing a newly constructed, approximately four-mile 230kV transmission line that would run to the Tribe's 230 kV bus at that substation.

Jobs, Revenue and a Target Date

The project assessment projected that construction could support up to 1,200 direct and indirect jobs over an estimated 18-to-24-month construction period, and separately projected an approximately 18-month construction timeline after permitting. On the revenue side, the assessment proposed up to $1.5 million per year in new trust lease payments to the Confederated Tribes of Warm Springs, plus up to $620,000 annually in new Tribal tax revenues.

The same assessment set a desired commercial operation date of December 31, 2027, though that figure is described only as a target the project hopes to reach, not confirmation that Salmonfly will be generating power by then. Earlier in the planning process, the assessment indicated that staff had recommended public review, with Tribal community input and Tribal Council consideration of the lease and build permit identified as the next steps at that time — a process that has since moved forward with the Council's October approval and this month's finalized lease.

Mitigating Impacts on First Foods and Wildlife

Beyond the construction timeline and dollar figures, the project plan sets parameters meant to mitigate impacts on wildlife habitat, first foods and culturally significant plant areas, according to The Bulletin. Those considerations carry particular weight on tribal land, where traditional foods and plant gathering sites hold cultural significance beyond their ecological value.

Salmonfly and PGE

Salmonfly isn't an isolated deal for Portland General Electric. Metal.com's coverage of PGE's build-transfer agreements notes that the utility signed a similar agreement for the Bigelow solar-plus-storage project, which includes 200 megawatts of solar and 250 megawatts of battery storage.