The Wayne Zoning Board of Adjustment voted 5-0 on Nov. 2 to authorize a conditional settlement with WPB Investors, the company behind a proposed inpatient drug treatment center that the board unanimously rejected just a year earlier. The deal does not guarantee the facility will be built. It only clears a path for WPB to come back with a revised plan, and only if a judge signs off on the settlement first.
According to TAPinto, WPB plans to return to the board for a public hearing on its revised plan if the court accepts the settlement. No hearing date has been announced. The site at the center of the fight is the former hospice at 220 Hamburg Turnpike, next to St. Joseph's Wayne Medical Center, where WPB had proposed housing 24 beds across 12 resident rooms, each holding two patients.
A Parking Count That Sank the Original Plan
The company behind the operation, JM&T Healthcare, would have run the treatment center, which was designed to keep a registered nurse on duty around the clock. WPB told the board that parking was the one zoning requirement it could not meet, and township records bear that out: a planning technical review found the township required 36 parking spaces for a 24-bed facility of this kind.
WPB's site plan proposed removing an existing generator and oil fuel tank to increase parking from 20 spaces to 23, according to the Township of Wayne planning technical review. That left the facility 13 spaces short of what the review calculated as required. The application sought a conditional-use variance because zoning allowed outpatient treatment, not inpatient services. WPB argued patients would generally arrive without cars and that staff and visitors could rely on shared parking across the hospital campus.
Inside the Hearing That Led to Denial
The board held a hearing on WPB's original proposal in November 2025, where the parking question dominated discussion. Board member Steve Toth asked whether more accessible parking was needed, noting the accessible spaces were already full during the day, while WPB traffic engineer Corey Chase said the slope between the lower and upper parking lots was too steep for an accessible walkway. WPB attorney Larry Calli agreed to try to add an accessible space in the lower lot, and St. Joseph's attorney Keith Loughlin spoke against the proposal.
Addressing the board, Timothy Jackson said patients would come voluntarily and that the goal was for them to stay about 28 days. None of that testimony changed the outcome. Board member Hilary Caruso moved to deny WPB's application, Ahab Husein seconded the motion, and the board's seven voting members voted unanimously to deny it. The board formally adopted its written denial in January.
From Denial to Lawsuit to Settlement
WPB sued the zoning board in Passaic County Superior Court in late February, asking a judge to order the board to approve its application and arguing the board had disregarded its experts' testimony. As reported by NJ.com, the lawsuit asked the court to reverse the denial outright and grant preliminary and final major site plan approval. The outlet's reporting also noted that even with the lot restriping, WPB's proposal included only 23 parking spaces, 13 fewer than required, underscoring the gap that had doomed the plan at the board level.
The zoning board responded that spring, telling the court that evidence supported its decision and asking the judge to dismiss the case. Rather than let that fight play out in court, the two sides negotiated instead. Township planner Christopher Kok said the parties agreed on terms covering security, outdoor space, recreation, meals and parking, and said that if the court approves the settlement, WPB would return for what Kok referred to as the Whispering Woods hearing.
What Happens Next
WPB will explain at that future public hearing exactly what it agreed to change from its original proposal, and the board will vote on the application at that session. For now, the settlement's fate rests with the court, and the revised plan is set to be explained at the future hearing. This is not the township's first clash over an inpatient addiction facility; a separate proposal at 1777 Hamburg Turnpike was denied by Wayne's zoning board in March 2021, according to a TAPinto report on the township's broader zoning posture toward in-patient medical offices in residential neighborhoods.