Boston/ Transportation & Infrastructure

Westfield Water Plant Gets $19M Loan Break as PCB Delays Loom Over 2028 Deadline

AI Assisted Icon
Published on November 11, 2026
Westfield Water Plant Gets $19M Loan Break as PCB Delays Loom Over 2028 DeadlineSource: Springfield Water and Sewer Commission

Ratepayers across the Springfield area are getting a break on the cost of a massive new water treatment plant, after the Massachusetts Clean Water Trust forgave $19 million of a $50 million loan tied to the project. The announcement, made Monday, covers the new West Parish Water Treatment Plant under construction at the Springfield Water and Sewer Commission's Westfield facility, a project with an estimated cost of $363.8 million that is scheduled to be complete in 2028.

A $19 Million Break for Ratepayers

Jaimye Bartak said the forgiveness would save ratepayers $19 million in direct costs and interest payments, according to MassLive. Bartak also said the plant will provide drinking water for a quarter-million people once it becomes operational. Governor Maura Healey said the broader round of loan forgiveness, which totaled $108.1 million across 46 Massachusetts projects, would help communities upgrade wastewater systems, protect public health and keep costs down, and said it would benefit 35 communities statewide.

The Springfield Water and Sewer Commission has separately described its own figures for the project's financing on its dedicated project website. The commission says it has received $16.9 million in loan forgiveness tied to a $65 million competitive low-interest loan awarded to the commission in 2024, representing 37.7% of that loan, according to the Springfield Water and Sewer Commission. The commission says that forgiveness is to be awarded upon completion of the project in 2028, and notes the project was the top-ranked drinking water project on the Clean Water Trust's 2024 Intended Use Plan.

Why the Old Plant Has to Go

The commission's current method of treating organic material in the water has led to high levels of disinfection byproducts since 2018, byproducts that can cause cancer if consumed over years. The commission says its 1974 West Parish Filters plant was not designed to meet today's disinfection-byproduct regulations, and that building a new plant will resolve those exceedances, per the commission's own administrative consent order notice. Climate change may be making the problem worse, with the commission noting that more intense and extreme precipitation patterns in recent years are increasing the amount of natural organic matter flowing into Cobble Mountain Reservoir.

The fix is a treatment process called dissolved air flotation, which the new West Parish plant will use to increase removal of organic material from the water. The commission says the technology was identified through on-site pilot testing at West Parish Filters between 2018 and 2020 as the method that most effectively limits the formation of those disinfection byproducts, and that it will help the plant meet federal water standards.

Funding Stack and a Delayed Timeline

The new treatment plant is being funded through a mix of sources: a $250 million low-interest loan from the U.S. Environmental Protection Agency, matching funds from the state's Drinking Water State Revolving Fund, and congressional earmark funding. The loan forgiveness funding itself came from the federal Infrastructure Investment and Jobs Act. A spokesperson for the Office of the State Treasurer and Receiver General said the forgiven-loan percentage was based on recipients' disadvantaged communities ranking, which considers factors including employment rate and per capita income.

Officials held a groundbreaking ceremony in Westfield in October 2024. The commission's consent order sets a construction-completion date of September 30, 2028, but a MassLive report from April 2026 said the project's expected final completion had shifted to November 20, 2029, after contractors found PCBs in caulking in the old plant. That same report said contractors estimated the PCB-related issues could put the project $8.5 million to $31.5 million over budget. Portions of the project were put on hold earlier in 2026 as a result.

Work Underway in Westfield

On the ground, construction crews have spent the weeks before publication removing demolition debris from the site, and have been working to encase water transmission pipes roughly 5 to 6 feet in diameter in concrete. The commission previously received smaller rounds of loan forgiveness for the broader project, including $5.9 million from the Clean Water Trust for Phase 1 work that included a new Backwash Facility completed in 2023, and $4.47 million in loan forgiveness that same year.

Springfield was not alone in Monday's round of state forgiveness. The Massachusetts Clean Water Trust also forgave $220,400 of a $1.16 million loan to Chicopee, which used its loan funding to create a comprehensive wastewater management plan. The Trust, working alongside MassDEP, has said its broader mission is to help communities build or replace water infrastructure that protects public health and supports resilient water systems, according to the Massachusetts State Treasury.