
Skokie officials say they have found a developer willing to pick up the pieces of the village's long-stalled downtown hotel project, more than three years after construction crews walked off the site at 4930 Oakton Street. Murphy Development Group, a Chicago-based firm, has emerged as the frontrunner to take over the unfinished Homewood Suites by Hilton, though it is not yet the chosen developer and still needs sign-off from village leadership.
The identification of Murphy as the leading candidate was confirmed following a Skokie board meeting on October 5, according to the Chicago Tribune. Village attorney Rodney Lewis said Murphy took the lead among the field of interested developers, though the firm must still submit final numbers on expected completion costs before village officials can act. Separately, The Real Deal described Murphy as leading a field of eight developers vying for the project, a count that differs from the broader tallies Skokie has cited over the past several months.
Murphy Development Group has submitted a formal design plan and intends to continue the hotel concept originally envisioned for the site, according to the seed reporting. The firm is not a stranger to downtown Skokie: it previously developed Highpoint at 8000 North, a 12-story, 153-unit luxury apartment complex at 8000 Lincoln Avenue, which REBusinessOnline reported opened under Murphy's ownership.
A Construction Site Frozen Since 2023
The Homewood Suites project has sat partially built since construction halted in July 2023, as reported by The Record North Shore. The property, intended to become a Homewood Suites by Hilton, was developed and owned by E&M Strategic Development before the project collapsed into litigation and foreclosure. A third-party structural engineer reported in October 2025 that the building remained structurally sound, though the Tribune's June reporting noted some elements required ongoing monitoring.
The legal tangle began when lender X-Caliber Capital sued E&M Strategic Development in February 2025, alleging the developer had defaulted on its construction loan because of cost overruns, according to the village website. Russell Construction separately sued E&M over allegedly unpaid project costs. Skokie Village was originally named as a defendant in the litigation, but a judge has since absolved the village of responsibility and direct involvement in the pending case.
Arbitration Looms Over Any Deal
An arbitration panel held a hearing for all involved lienholders in September, and it is scheduled to decide on October 23 whether to grant a temporary stay or reschedule arbitration altogether. Lewis said he expects the panel to extend the stay, giving the parties more time to negotiate. Skokie officials have coordinated meetings among those parties and are asking lienholders to discount their demands as part of that effort, though the village maintains it is not a party to the litigation itself.
The village has already sunk approximately $10.5 million in Oakton-Niles TIF funding into the site, under an agreement that allows up to $13.5 million, per the Village of Skokie's own project page. A $4.5 million, 10-year loan authorized in 2023 was never actually disbursed, because the developer at the time failed to secure the additional financing required to trigger it.
How Many Developers Are Really in the Running
Just how many groups have looked at the site depends on when you ask. Skokie's government site says officials have been in communication with more than a dozen interested parties, while the Tribune reported in June that the number had grown from more than 10 in May to 13 by early June, with seven still in active conversations and three conducting underwriting. The Record North Shore reported separately that five developers had requested financial documents, with one group progressing as far as calculating completion costs. The Real Deal, for its part, described the current field as eight developers. Village officials say Murphy is now the clear frontrunner among whichever count is accurate, but the firm still needs the board's formal signoff before taking on the project.
It would not be the first time a hotel developer here has had to be swapped out midstream. Skokie's broader 8000 North downtown development previously stalled when its first selected developer could not secure financing, forcing the village to find a replacement, according to Patch. The hotel itself was first pitched in 2020 as a cornerstone addition to downtown Skokie and the Illinois Science and Technology Park, per Patch's earlier coverage of the project's approval by village trustees.
Why the Village Keeps Pushing
Skokie's government page states the finished hotel is projected to draw 100,000 annual visitors to downtown, underscoring why officials have stayed engaged even without a formal stake in the litigation. The village says it is actively seeking developers capable of completing the project, but it has repeatedly stressed that it cannot offer a timetable for when construction might resume because it is not a participant or partner in the deal.
Mayor Ann Tennes plans to provide the next hotel-project update before the end of the year, and that update will likely hinge on the outcome of the October 23 arbitration decision. The Skokie board has said it will continue providing regular status updates to residents as the situation develops.









