Gallatin's City Council voted 5-2 at a work session to let consultants move forward with design work on a compact, three-story City Hall, rejecting a last-minute push to hand the decision to the incoming administration instead. The vote came during a work session on November 10, and it does not authorize construction — it simply clears the way for further design on what's known as Option B.
The decision followed a tense debate over timing. Council member Todd Alexander had moved to defer the choice to the January 12 work session, telling colleagues, according to WKRN, to “move this to the January 12th work session and let the new council make that decision.” Alexander pointed out that five people around the council desks would change in January: Mayor-elect Johnnie Anderson and four incoming council members. That deferral motion failed 5-2, with Alexander and council member Pascal Jouvence voting in favor and the rest of the council opposed.
Why Some Pushed to Wait
Jouvence argued that spending more money before the new council had a chance to weigh in risked being wasted effort, saying he opposed moving forward until the incoming members could decide for themselves. Several council members, per Citizen Portal, urged caution until financing and legal issues tied to the broader downtown redevelopment were clarified.
Council member Craig Hayes pushed back hard against waiting, arguing the city had already studied the issue for two years and that a successor council would have only about a week to review the matter before any January decision. Hayes made the motion to advance Option B, and member Steve Fann agreed with him. Council member Steven Carter added that the council should make difficult decisions rather than keep postponing them.
What Option B Actually Looks Like
The study behind the vote came from Studio Eight Design, hired by the city to assess City Hall's space needs. Anna Ruth Kimbro presented the firm's overview, explaining that the assessment established current and projected department square footage needs looking 20 years ahead, drawing on interviews with current department heads. The engineering department's planned move into City Hall, rather than the public works building, has added to the required square footage.
Studio Eight laid out two options. Option A would renovate the existing City Hall and add a two-story Main Street addition, while Option B calls for a new, compact three-story building on the existing site — about 18,000 square feet smaller than Option A, according to the firm's figures. Kimbro said Option A would provide substantially more square footage overall, but that includes renovated space, the addition, and unusable basement area. She said Option B's smaller footprint, stricter building envelope requirements and single building system would likely lower long-term costs, and that cost opinions in the first phase of the study were based on price per square foot, with a second phase adding preliminary block plans, site test-fit plans and cost estimates beyond a single figure.
Parking, Site Slope and the Basement Problem
Part of the complexity stems from the site itself, which slopes from Main Street down to Franklin Street. Studio Eight's parking study weighed grade-level parking combined with subgrade parking beneath the new footprint against an all-below-grade option that would require excavating four to five feet deeper than the existing basement. Kimbro said the deeper, fully subgrade option would only make sense if the city wanted to preserve the site for future development, and the firm's cost projections for Option B include subgrade parking beneath the new footprint only.
Current City Hall's roughly 13,000-square-foot basement is suitable for storage and operations but not occupied office space, while the main level is better suited for loading and moving items at grade because of elevator issues. Council member Paul Jones, who said he previously worked in the basement, told the council the space “smelled as bad or worse” than when he worked there and argued a new building could improve conditions for everyone.
An Aging Building Driving the Push
The push for a new building rests heavily on the condition of the current structure, which opened in 1975. A 2020 assessment from Gresham Smith and Partners found City Hall's building systems were past their operational lifetime and needed full or substantial replacement, a conclusion Studio Eight's own assessment echoed. Officials say the building needs security upgrades, extensive ADA upgrades and a sprinkler system to meet current codes.
Rosemary Bates, executive director of Gallatin's economic development agency, put it bluntly: “It is not ADA compliant. It is not sprinkled. It smells. It's got mold in the downstairs,” she said, as reported by the same WKRN account. Hayes said he favored a new City Hall based on its costs and other benefits over sticking with the aging structure.
How This Fits Into Project Phoenix
The City Hall decision unfolds alongside Project Phoenix, a larger downtown redevelopment proposal involving developer Boyle that would add housing and retail to downtown Gallatin while also reconstructing City Hall and relocating the Gallatin Fire Department headquarters, according to WKRN. Kimbro noted that the possible size of a new City Hall was established separately from Project Phoenix, and that a new building could be placed anywhere on the site if the city ultimately does not move forward with the redevelopment plan. Bates said either City Hall plan could proceed regardless of what happens with the Boyle development.
Option A would cost between $1 million and $1.2 million more than Option B, per the cost opinions presented to the council, though a final price tag for either path has not been publicly released. Concerns over cost transparency aren't new to the broader redevelopment conversation — a petition pushing city leaders toward more transparency on the project drew more than 100 signatures earlier.
For now, the council's 5-2 vote only authorizes Studio Eight to continue design work on Option B; it does not commit the city to building anything. The ultimate decision — and its price tag — remain unresolved as the council prepares for a membership change in January 2027.