Hideaway Beach Club's nine-hole course was officially given new life Tuesday, after some people had tried it early, following a $5.6 million renovation that rebuilt greens, reworked hole layouts and replaced the drainage system. The drainage work was a central part of an overhaul of the course, which was built in the 1970s.

The club completed the renovation this month, spending $5.6 million on the golf course improvement, according to Coastal Breeze News. Combining drainage work with the golf course renovation saved the community an additional $1.5 million, the outlet reported. The project also expanded greens and hole layouts and enhanced teeing areas.

The Course’s Drainage Challenges

The course had not been significantly overhauled since it was built and experienced three major floods over the prior 20 years, including during hurricanes Ian and Irma, according to Coastal Breeze News. A 2025 account from marconews.com said the reconstruction was scheduled for the following year and would address drainage problems involving water outflow into the Gulf.

Hideaway Beach Club General Manager and Chief Operating Officer Eamon Murphy described the former layout as “classic, old-school Florida,” Coastal Breeze News reported. Murphy said the redesign brought the course from average to a level comparable with professional-grade courses across southwest Florida. He also said feedback on the renovated course has been outstanding and that the later holes differ dramatically from the previous layout.

A Rebuilt Course and Drainage Network

Golf course architect Kipp Schulties designed the renovation, which incorporated about 100,000 cubic yards of new fill, Coastal Breeze News reported. The work reshaped the course with raised terrain, varied sand traps and larger lakes. Greens doubled in size while remaining within the original footprint, giving the superintendent more options for moving pins and holes from day to day.

Golf course superintendent Dustin Black said the course is among a handful in southwest Florida using TiF3D ultra-dwarf Bermuda grass, which is known for durability under environmental stress and for retaining its emerald-green color year-round, according to the report. TiF3D's own product site, tif3d.com, describes the grass as a premium ultradwarf bermudagrass bred by the University of Georgia for putting-green performance. Black described the new greens as championship-level.

The redesigned drainage system is intended to move water more easily during excessive rainfall and connects the lakes through a series of large pipes, Coastal Breeze News reported. Murphy separately told marcoareaexpert.com that the course’s lagoons filter drainage before it is released into the Gulf.

What Storm and City Records Show

The course reporting identifies flooding at Hideaway Beach during storms that included Irma and Ian, but the National Hurricane Center record provides regional context rather than documenting flooding at the golf course: it says Irma made its final landfall near Marco Island at 1930 UTC on Sept. 10, 2017. The material cited here does not establish where or how flooding occurred elsewhere on Marco Island or provide an official comparison of Irma’s and Ian’s impacts.

A Signature Sixth Hole

The sixth hole now has water on both sides and a sand trap in front of the green, according to Coastal Breeze News. Murphy said players need two accurate shots to reach par, making the hole an example of how the redesigned course differs from its decades-old layout.