Memphis-Shelby County Airport Authority officials have approved a $98.66 million contract to begin construction on Terminal B, the latest step in a modernization push that has already drawn $398 million in total funding commitments for the airport's aging terminal complex.
The contract approval, reported Wednesday by Memphis Business Journal, marks a concrete construction milestone for a program that has been years in the planning. According to the outlet, the airport authority's CEO expects the next funding approval, anticipated in spring 2027, to push the program's total modernization funding up to $800 million. That figure is described as an expectation rather than a locked-in commitment, and the exact steps required to get there haven't been detailed publicly.
What the Terminal B Work Actually Involves
The broader effort is known as the Terminal Modernization and Seismic Program, or TMSP, and its goal is the modernization, expansion and seismic upgrade of the existing commercial terminal building, according to MFA Program Management, which also notes the work extends to the pedestrian and roadway curb-front infrastructure surrounding the terminal. The same materials describe plans to upgrade aging mechanical, electrical, plumbing and baggage systems while balancing concourse capacity, and to add remote check-in options for travelers.
Designers also say they're trying to preserve the terminal's distinctive “martini glass” shape even as they build in flexibility for future technology and passenger-processing needs, per the program materials. That architectural signature has long been a point of local pride for the airport, and keeping it intact appears to be a deliberate design constraint rather than an afterthought.
Terminal B Fits Into a Larger Phase II Push
Terminal B's construction is part of what the airport calls Phase II of its terminal work, following the completed concourse modernization that made up Phase I. Memphis International Airport's own construction page states that the modernized concourse opened on February 15, 2022, before the focus shifted to terminal renovations.
Phase II's scope is substantial. The airport's construction materials describe relocating and reconfiguring vertical circulation, building a Checked Bag Inspection System, and expanding the security screening checkpoint. The same page says the work also includes constructing an employee screening checkpoint and preparing space for a future Federal Inspection Station to handle international arrivals — infrastructure MEM does not currently have in place.
Seismic Prep Work and Funding Source
A construction request for proposals covered by The Daily Memphian describes enabling renovations meant to prepare Terminal B for seismic modernization while also improving finishes in Terminals A and C. That early release package includes a new entrance addition, improvements to the existing building enclosure, and upgrades to mechanical, electrical and fire protection systems, according to the outlet.
Notably, the airport has stated that MEM receives no local tax revenue for any of these projects, a point emphasized on its construction information page. A separate airport update citing contractors UrbanArch and Alliiance listed the Terminal Building Modernization component as starting in 2027, aligning with the broader timeline now taking shape around the newly approved Terminal B contract.
With $398 million already committed and a potential jump to $800 million on the table for spring 2027, the airport authority's board appears to be setting up a multi-year construction sequence. Just how passengers will experience that work as it unfolds — and the precise order in which terminals get touched — hasn't been spelled out in the materials released so far.