The ambitious plan to transform Milford's Connecticut Post Mall with as many as 750 new apartments has collapsed, according to city planning staff, who say mall owner Centennial has indicated it cannot deliver the mixed-use redevelopment it promised three years ago. Now the city is moving to rewrite the zoning rules that made that vision possible in the first place.
A Promise That Never Materialized
According to The Connecticut Examiner, reporter Nick Sambides Jr. detailed how the Connecticut Post Mall owner has dropped its plan for the 750 apartments once envisioned for the Milford shopping center. The mall itself sits in Milford, Connecticut, and has long been one of the region's largest retail properties, making any redevelopment there a significant local story. Milford planning director Dave Sulkes said the previous 2023 mixed-use vision for the mall is unlikely to proceed, according to citizenportal.ai, which reported that mall ownership had indicated it cannot deliver the previously promised redevelopment.
Planning staff have responded by recommending the city rescind the 2023 RMF-16 provisions that had been written into the Shopping Center Design District specifically to accommodate the project, the outlet reported. Rather than scrapping housing at the site altogether, staff want to tighten the district's standards to protect community interests while still allowing mixed-use residential development that meets the requirements of a newer state statute, per the same account. It is a notable reversal from the optimism that surrounded the project when it was first approved.
How the 750-Unit Plan Came Together
The zoning change traces back to October 2023, when Milford's Planning and Zoning Board voted 7-0, with Vice Chairman Robert Satti abstaining, to approve amended city zoning codes allowing the mall owner to seek approval for a mixed retail-and-housing redevelopment, according to the Milford Mirror. Those rule changes opened the door to as many as 750 dwellings, including up to 75 affordable-housing units, phased in over the following decade.
By the spring of 2024, the project appeared to be gaining momentum. A report from ctpost.com in April of that year described the plan to build as many as 750 apartments as part of a mall redesign as moving forward. The zoning amendment ultimately allowed the apartments to be built in three phases of no more than 250 units each, with 10 percent of the units in every phase required to be set aside as affordable housing, the outlet's reporting showed.
No Design Ever Materialized
Even as the timeline stretched on, the paperwork never caught up with the ambition. As of March 2025, the mall's owner still had not submitted a proposed design for the apartment project to city officials, even though the city's chief of staff said at the time that Centennial was expected to share renderings within weeks, ctpost.com reported. That gap between promise and paperwork appears to have persisted for the better part of a year before culminating in the plan's apparent abandonment.
What remains unresolved is exactly which parts of the original redevelopment Centennial has abandoned, and whether the Planning and Zoning Board has formally acted on staff's recommendation to rescind the 2023 provisions. No replacement plan, revised timeline, or statement from Centennial explaining the company's decision has been documented in available reporting. For now, Milford's planning staff appear focused on rewriting the rules rather than waiting on a developer who has already signaled it cannot follow through.