Concrete crews at O'Hare International Airport are building the guts of a $250 million facility that will keep the airport's next generation of terminals from ever breaking a sweat. Work on the Midfield Cooling Plant began in earnest last month, with crews pouring concrete on October 13 and following up the next week by installing precast concrete walls. The plant is expected to be finished in 2028.
The project is part of the sprawling ORDNext expansion program reshaping O'Hare, according to Urbanize Chicago. Once complete, the plant will cool the new Concourse D, the new Concourse E, and eventually the O'Hare Global Terminal, giving the airport's biggest building projects in decades the air conditioning and chilled water they'll need to function. The Chicago Department of Aviation and its design and construction partners determined that O'Hare's existing heating and refrigeration plant, located next to Terminal 3, simply could not provide enough capacity to cool an airport this size once the expansion is finished.
How the System Will Actually Cool the Airport
The Midfield Cooling Plant will function as a hydronic cooling system, chilling water that then gets pumped through cooling coils inside air handlers scattered across the new ORDNext terminal facilities. That chilled water will travel through 8,600 feet of piping, reaching as far as 2,500 feet from the plant itself, per the same Urbanize Chicago report. Water will leave the plant at about 42 degrees Fahrenheit and return at roughly 55 degrees after absorbing heat from the terminals.
At peak load, the system is designed to circulate more than 300,000 gallons of water, according to the outlet's reporting. A separate city posting describes the mechanical heart of the operation as four water-cooled centrifugal chillers, each rated at 3,200 tons, for a combined 12,800 tons of cooling capacity, though that figure comes from a search-result snippet on chicago.gov rather than a fully verified page.
Why Consolidate Cooling Into One Plant
Water-cooled chillers typically use less energy than their air-cooled counterparts and are commonly found in large campus environments like airports and universities, the report notes. By consolidating cooling capacity into a single new facility rather than scattering smaller units throughout the terminals, the airport expects to lower both maintenance and energy costs while reducing mechanical loads elsewhere on the property. That consolidation is also meant to free up more space inside the terminals themselves for passenger amenities, back-of-house operations, and other mechanical systems.
O'Hare International Airport on X
wrote that the plant will use 8,600 feet of piping to cool future terminal facilities, calling it “the coolest part of #ORDNext.”
Concourse D's Steel Is Already Rising
The cooling plant isn't the only piece of ORDNext visibly taking shape. The new Concourse D is under construction nearby, with vertical steel construction already taking shape, per the Urbanize Chicago report. That project, a 19-gate, 580,000-square-foot concourse valued at $1.45 billion, broke ground in August 2025 and had completed roughly 35% of its foundational work by the time Facilities Dive reported on its progress. Plans for the concourse call for more than 20,000 square feet of lounge space alongside 30,000 square feet of retail and dining.
Construction Dive's earlier coverage described the same project, referred to there as Terminal D, as the first of two new satellite concourses planned under the broader ORD Next modernization effort. Its design includes 19 gates built for narrow-body aircraft, with 18 of those gates able to be adapted into nine larger ports for wide-body planes, according to Construction Dive. That outlet reported vertical construction was scheduled to begin in spring 2026, with the work wrapping up in 2028, and it described roughly $300 million in related infrastructure improvements, including a central cooling facility situated in the middle of the airfield.