Miami/ Politics & Govt

Palm Beach County Data Center Tripled Days After Lawyer's Threat Over Project Tango

AI Assisted Icon
Published on November 26, 2026
Palm Beach County Data Center Tripled Days After Lawyer's Threat Over Project TangoSource: İsmail Enes Ayhan / Unsplash

A lawyer representing the developer behind Palm Beach County's Project Tango data center sent county officials a 180-page letter warning of potential financial liability if a proposed expansion was denied, and ten days later, county zoning staff approved the expansion without another vote from commissioners. The timeline has left nearby residents and at least one county commissioner questioning how the approval happened at all.

According to WPTV, attorney Ethan Loeb sent the letter threatening legal action if county staff did not approve the expansion, and it warned that denying the project could cause significant and potentially catastrophic financial liability for the county. The letter also claimed the damages PBA Holdings could recover might be financially unsustainable for Palm Beach County, and it challenged requirements for continuous sound studies and real-time public noise monitoring, alleging the county had never imposed those requirements on another property owner. Perhaps most strikingly, the letter reportedly included not just legal threats against the county but a personal legal threat against zoning director Wendy Hernandez.

The letter followed a July 15 vote in which five of the county's seven commissioners rejected a larger version of the Project Tango proposal, which had sought more than 1 million square feet of data-center space after a marathon 12-hour hearing, as reported by WPTV. Commissioner Katherine Waldron, who represents the area where the data center would be located, said the threat against a county employee calls the approval process into question.

Figures on the Expansion Diverge

Sources differ on exactly how much space county staff ultimately signed off on. WPTV has reported the approved footprint grew from 206,000 square feet to just under 700,000 square feet, while the Sun Sentinel reported the Oct. 7 approval added 546,000 square feet, bringing the total to nearly 700,000 square feet. Either way, the October approval allowed Project Tango to roughly triple its data-center space, and it came without another vote by county commissioners or a new public hearing before the commission.

The Sun Sentinel's reporting notes that commissioners are now calling for a potential change to the county's approval process in the wake of the administrative sign-off. The newspaper also reported that the recent administrative approval did not require a review by county commissioners at all — a detail that has fueled frustration among residents who thought the July vote had settled the matter.

Residents Who Fought the Project Feel Blindsided

Janice Ridenour, who lives near the Project Tango site in Arden and helped lead western communities' opposition to the original expansion proposal, said the letter was shocking. She told WPTV that residents spent money on lawyers and felt their efforts were for nothing after the October approval went through administratively. Waldron and Ridenour both fear the precedent could extend further, allowing light-industrial warehouse properties elsewhere in the county to be administratively approved for data-center use without ever coming before commissioners for a vote.

Waldron said the circumstances surrounding the October decision raise the question of whether it should be reconsidered. WPTV reports it will continue following whether the county moves to nullify or revisit the approval; the station's reporter, Michael Hoffman, contacted Project Tango's developers for comment on the expansion but did not receive a response.

Litigation and a Countywide Pause

The legal wrangling didn't end with the letter. PBA Holdings filed a lawsuit on Oct. 9 over the county's handling of an appeal process, then voluntarily dismissed it without prejudice, according to the Sun Sentinel. The company's dismissal motion said it believed the county had since complied with the process, though the without-prejudice dismissal means PBA Holdings could sue the county again in the future. Assistant Palm Beach County Attorney Maureen Martinez had filed a motion to dismiss the complaint on Nov. 2, shortly before PBA Holdings dropped the case.

The dispute unfolded against the backdrop of a broader countywide pause on large data-center projects. County commissioners voted 6-0 on Sept. 24 to pause new applications for large data centers for up to a year, according to CBS 12, applying to proposals in unincorporated areas of the county with anticipated peak electrical loads of at least 50 megawatts. That moratorium is set to run for a year or end sooner if the county adopts permanent rules, and county staff have flagged noise, electricity and water use, water disposal, and compatibility with nearby properties as issues to study before writing those rules. The pause does not appear to have applied to Project Tango's previously submitted application, which moved forward through the administrative process regardless.

A WPB Logistics application that could add roughly 1.2 million square feet of data-center space on another portion of the Project Tango property remains under review, according to WPTV's reporting — a sign that the fight over how much data-center growth the county should allow is far from over.