Pembroke Pines Owners Still Wait to Rebuild After 2021 FireSouth Florida Apartment Reconstruction
Zoshua Colah / Unsplash

Five units in Building Seven at Westview Condominiums in Pembroke Pines are still uninhabitable, more than five years after a fire broke out there on February 16, 2021.

The latest word from the company that manages the board is that revised reconstruction plans are finished and with the city. A construction start is not. WSVN 7News reported the fire destroyed five units, and that those homes remained unlivable when owners were interviewed this week.

Who Lost the Units

Frederique Auguste bought her unit in 2010 for her daughter's family. Nestor Palma, who retired after 20 years in the U.S. Navy, bought his in Building Seven in 2015. Investigators believe the fire may have started next to Auguste's unit.

Palma is renting an apartment in Maryland because the condo was destroyed. He hopes to move back to South Florida. He and Auguste both said they have not received updates about the rebuild.

Mortgages on Homes They Cannot Use

The carrying costs did not pause with the walls. Palma and Auguste continue to pay mortgages, property taxes, and nearly $700 a month in association fees on units they cannot occupy.

Auguste said, "I'm out about $100,000 at this point within these last five and a half years." She also said she cannot afford to sue the association. A lawsuit, in her account, is not a practical route back into the building.

Revised Plans, No Start Date

Association Services of Florida manages the condo board. A representative said the association has completed revised plans for the reconstruction of Building Seven, that the City of Pembroke Pines is reviewing them, and that the company is discussing the permitting process with the city.

"We do not yet have a confirmed construction start date," the representative said. Completed drawings, in that account, are still a step short of a crew. Palma said he is skeptical of the update and questions why the wait has stretched five years.

Letters, Meetings, and the Repair Duty

Auguste said she sent the board letters seeking insurance records, future architectural plans, and board meeting minutes, and that the letters went unanswered.

Under Florida condominium law, a board must respond in writing within 30 days after receiving a residential unit owner's inquiry sent by certified mail. Meetings at which a quorum is present are open to all unit owners, and owners have a right to ask questions there about reports on construction or repair projects. For a residential association with more than 10 units, the board must meet at least once each quarter, and at least four meetings a year must include a chance for members to question the board.

The same chapter requires an association to repair or replace common elements such as walls, ceilings, and roofs. None of that puts a date on Building Seven. The plans remain in city review, permitting is still a discussion, and Palma is still paying for a Maryland rental while he waits for a reason to come home.