Strongsville City Council is set to vote Thursday on a $553,143 settlement with Heritage Pool Supply Group Inc., known locally as EMSCO, closing out a lawsuit over a 2024 chemical spill that sent chlorine gas into a city sewer pump station and sickened nearby construction workers. The vote is scheduled for a special meeting at 5 p.m. in the Mike Kalinich Sr. City Council Chamber.
The proposed deal, detailed by cleveland.com, would end the case before it reaches trial. Under its terms, EMSCO would pay Strongsville $553,143, with the settlement requiring payment within 14 days after both sides sign. The agreement would also bar either side from suing the other again over the spill and require each side to cover its own legal fees.
The trouble traces back to EMSCO's facility on Royalton Road, where, according to the city's lawsuit, rainwater collected around storage tanks holding sodium hypochlorite and one of the tanks sprang a leak. EMSCO workers pumped out and drained the contaminated water into the sewer on the mornings of June 17, 18 and 19, 2024. The lawsuit says the workers treated the water first but did not test it before letting it go.
EMSCO was founded in 1969 in Strongsville as a family-owned pool and spa products distributor. Heritage Pool Supply Group acquired EMSCO and another distributor, OP Aquatics, in December 2021; at the time, EMSCO operated branches in Ohio, Pennsylvania and Kentucky and employed more than 80 people. The acquisition announcement said EMSCO’s existing leaders would continue running the business under its local brand. Heritage’s announcement of the acquisition described the company’s history and regional footprint.
Vapor Cloud Sickened Workers Near Westwood Lift Station
That water flowed to the Westwood Lift Station on Westwood Drive, which was in the middle of being rebuilt at the time. Construction workers at the site reported seeing a vapor cloud on each of the three mornings and said they suffered burning eyes, coughing, trouble breathing and headaches. Firefighters were called out each day of the incident, and the lawsuit says the road near the lift station was closed during each response.
The Northeast Ohio Regional Sewer District traced the vapors back to EMSCO and cited the company for the discharge the following day, on June 20, 2024. The following month, per a letter cited in the lawsuit, EMSCO acknowledged that approximately 700 gallons of water containing sodium hypochlorite had been drained into the sanitary sewer, matching the amount the settlement itself puts at about 700 gallons. In that same letter, the company said the leaks had been fixed and that it would hold and test water before draining it in any future incident.
Industrial wastewater entering public sewers is subject to a regulatory framework intended to protect sewer systems and treatment plants. Ohio’s pretreatment program operates under the federal Clean Water Act, with Ohio EPA delegating oversight to local governments in many cases. The Northeast Ohio Regional Sewer District says it has operated an EPA-approved industrial pretreatment program since 1984 and uses inspections and monitoring to address industrial pollutants entering its sewer system. The district’s industrial-waste program outlines that authority and its pollution-prevention work.
Chlorine Gas Wrecked Brand-New Equipment
The damage went beyond the vapor exposure. The lawsuit says chlorine gas damaged brand-new electrical equipment at the pump station that had been made by Schneider Electric. The manufacturer warned that the damaged equipment could spark dangerously and recommended replacing all of it, and the equipment's warranty was cancelled as a result of the harm.
Sodium hypochlorite is commonly used in pool products, but its chemical behavior can create a serious inhalation hazard: the federal Agency for Toxic Substances and Disease Registry says it releases chlorine gas when it comes into contact with acids. That general hazard does not establish what caused the gas in this incident; the city’s lawsuit describes the discharge and resulting vapor, while the proposed settlement resolves the city’s claims without a trial. ATSDR’s chlorine fact sheet explains the reaction.
Strongsville ordered new electrical equipment, which the lawsuit says was expected to take nearly another year to make, ship and install, even though the Westwood Lift Station rebuild was supposed to be mostly finished by late August 2024. In the meantime, the city rented temporary pumps to keep its sewers running.
City Sued After Months Without Payment
Strongsville asked EMSCO to cover the costs tied to the spill, but according to the city, the company had not paid. The city filed suit against Heritage Pool Supply Group in May 2025. Per the terms now before council, Strongsville would drop the lawsuit once the settlement payment arrives, and the deal would take immediate effect only with a yes vote from at least two-thirds of council.